System task statuses
The three built-in system task statuses in Workfront are required, which means that you can unlock, rename, and reorder them, but you cannot hide or delete them.
You can also add new system task statuses to match the needs in your organization.
Changing the status of a task is typically a manual process. However, there are times outlined in the following list when the status of a task is changed automatically, depending on other factors that are happening in the system.
The following task statuses are provided with your Workfront instance:
When you mark a task as In Progress, the task shows a value for the Actual Start Date.
Progress on the task is not recorded until you manually update the percent complete of the task.
You can manually mark a task complete when the work on it is completed.
When the Tracking Mode of a task is set to Autocomplete, the task is automatically marked Complete when it reaches the Planned Completion Date.
When a task is completed, the percent complete of the task is marked as 100%. The task is removed from the assignee's My Work list in the Home area when it is completed.
When you mark a task as Complete, the task shows a value for the Actual Completion Date.
NOTE: If the task has incomplete issues and you change the task status to Complete, the status automatically changes to Complete - Pending Issues.