View task information in the project list Gantt Chart

You can view the task information for a project directly from the Project List. Tasks are listed under the name of each project.

NOTE
You cannot edit tasks from the Project List Gantt Chart.

You can view the task information for a project directly from a list of projects in the following areas:

  • In the Projects area
  • Within a Portfolio
  • Within a Program

To view tasks in a project from a list of projects:

  1. Go to one of the areas mentioned above.

    For example, from the Main Menu, click Projects.

    A list of projects displays.

  2. Click the Gantt chart icon Gantt icon in the upper-right corner of the screen.

  3. Click the Show Task List icon.

  4. In the project list to the left, click the drop-down arrow next to the name of the project to display any tasks under that project.
    This displays task information on the Gantt Chart.
    Show_task_list_enabled_project_expanded.png

  5. (Optional) Click the Print icon in the upper-right corner to export the Gantt Chart.

    NOTE
    The Project List Gantt Chart exports only projects. Task information is not included.

Change the time period for which information displays in the Gantt Chart

You can adjust the time period shown on the Gantt Chart to display information on a granular level, or you can quickly navigate to a day, week, month, quarter, or year view:

Change the time period on a granular level

  1. Hover over the timeline of the Gantt Chart, then drag the zoom indicator from left to right to expand or contract the timeline.
    zoom_tool_in_gantt.png

View information by Day, Week, Month, Quarter, or Year

  1. In the Gantt Chart, click the time frame drop-down menu.

    Timeline options

  2. Select a time frame from the following available options:

    • Fit All: This option displays the time line of the entire project.
    • All Projects: This option is available only in the Project List Gantt chart.
    • Year
    • Quarter
    • Month
    • Week
    • Day
  3. (Optional) Select a more granular time frame, such as Week or Day, and click and drag the horizontal scroll bar at the bottom of the Gantt Chart to move left to right on the time line of the project.
    A timeline snapshot of the Gantt displays to show the entire project.

    TIP
    The timeline snapshot displays only after you click the horizontal scroll bar.

    stretchy_gantt_minimap_with_outline__1_.png

  4. (Optional) Click anywhere inside the time line snapshot to navigate to a specific point in the life of the project.
    Or
    Drag the handles of the snapshot viewer to select a specific time line range to display it in the main Gantt.

Use filters, views, and groupings

The Gantt Chart is a visual representation of the information that is currently displayed in the task list. You can apply filters, views, and groupings to the objects listed in both Gantt Charts.

CAUTION
You cannot apply filters, views, and groupings when you select Manual save Timeline Planning to save changes to your task list. For information about saving changes to tasks in a list, see Edit tasks in a list.

Filters and groupings that you apply to the list are reflected on both the Project List and Task List Gantt Charts and are also included when the Gantt charts are exported:

  • Filters
    You can apply a Filter to the list in order to control the information that is displayed in the Gantt Chart.
    For information about applying a Filter, see Filters overview.

  • Groupings
    Groupings that you apply to the list are reflected on the Gantt Chart.
    For information about applying a Grouping, see Groupings overview in Adobe Workfront.

Views are not reflected on the Gantt Chart. However, when you export the Gantt Chart (as described in Export the Gantt Chart to PDF), the task list is exported in addition to the Gantt chart, with the current View applied to the list.

Configure Display Options

You can choose what type of information displays in both Gantt charts. For more information, see Configure how information displays on the Gantt Chart.

Previous pageConfigure how information displays on the Gantt Chart
Next pageUpdate information in the task list Gantt Chart

Workfront


Learn: Automating Workflows with Workfront Fusion - Unique Use Cases in Action

Workfront

Tuesday, Mar 4, 6:00 PM UTC

Looking for creative ways to use Workfront Fusion to solve business challenges? Join Pan Shahbazian of Starbucks as she shares three unique use cases that can transform your workflows.

Register

The Perfect Blend: A New Era of Collaboration with AEM and Workfront

Adobe Customer Success Webinars

Wednesday, Apr 2, 5:00 PM UTC

Explore how Adobe Experience Manager and Workfront integrate to help teams move from ideation to delivery without the usual bottlenecks, ensuring content is organized, on-brand, and ready to go live faster.

Register

Connect with Experience League at Summit!

Get front-row access to top sessions, hands-on activities, and networking—wherever you are!

Learn more

Register to learn something new

WORKFRONT

Join Adobe product experts in live events where you will learn Adobe Workfront best practices, tips and tricks, and hear about the latest product features and updates.

Register