Associate resource pools with one project or template

You can associate resource pools with a template in the same manner you associate resource pools with a project. This article describes how you can associate resource pools with projects.

  1. Go to a project and click the More icon More icon next to the project name, then click Edit.

  2. Click Project Settings.

  3. Start typing the name of a resource pool in the Resource Pools field, then select it from the list when it appears.
    You can associate multiple resource pools with one project or template.

    Project settings

  4. Click Save.

For more information about how to edit a project and associate it with resource pools, see Edit projects.

For more information about how to edit a template and associate it with resource pools, see Edit project templates.

Associate resource pools with several projects or templates in bulk

You can edit multiple projects or templates in bulk and associate the same resource pools with all of them at the same time.

You can associate resource pools with templates in the same manner you associate resource pools with projects.

To associate resource pools with several projects in bulk:

  1. Go to a list of projects.

  2. Select multiple projects, then click the Edit icon Edit icon at the top of the list.

  3. Click Settings.

  4. Start typing the name of a resource pool in the Resource Pools field, then select it from the list when it appears.
    You can associate multiple resource pools with the projects or templates.

    NOTE
    • When you edit templates in bulk, only the resource pools that are common to all the templates selected appear in this field. If the templates selected have no shared resource pools, this field is empty. The resource pools you specify here overwrite the individual resource pools of the projects or templates.

    • When you edit projects in bulk, there is a “Multiple values” indicator if the selected projects have different resource pools. If you add resource pools in bulk for projects, all the pools are added to the selected project, overwriting the original resource pools.

    add_resource_pools_to_multiple_projects.png

  5. Click Save Changes.
    When your resource pools are associated with your projects or your templates, you can budget user allocations for your projects inside the Resource Planner.
    For more information about the Resource Planner, see Resource Planner overview.

For more information about how to edit projects in bulk, see the “Edit projects in bulk” section in Edit projects.

For more information about how to edit templates in bulk, see the “Edit templates in bulk” section in Edit project templates.

Previous pageCreate resource pools
Next pageAssociate resource pools with users

Workfront