Overview of default constraints

When you create new tasks, a Task Constraint is automatically selected by Workfront.

Workfront uses two variables to decide which Task Constraint is selected by default for a new task:

The following table shows the default Task Constraint when choosing different variables for your project and your new tasks:

Project Schedule FromTask Start DateTask Constraint Default
Start DateBased on the Project Planned DateAs Soon As Possible
Start DateTodayStart No Earlier Than
Completion DateBased on the Project Planned DateAs Late as Possible
Completion DateTodayStart No Later Than