Overview of default constraints
When you create new tasks, a Task Constraint is automatically selected by Workfront.
Workfront uses two variables to decide which Task Constraint is selected by default for a new task:
-
The Project Schedule From field on the project.
For information about the Project Schedule From field, see Edit projects.
-
The Start Date preference configured by your Workfront or group administrator in the Tasks & Issues area of Setup.
For information about Tasks & Issues Preferences, see the New Task Defaults section in Configure system-wide task and issue preferences.
The following table shows the default Task Constraint when choosing different variables for your project and your new tasks:
Project Schedule From | Task Start Date | Task Constraint Default |
---|---|---|
Start Date | Based on the Project Planned Date | As Soon As Possible |
Start Date | Today | Start No Earlier Than |
Completion Date | Based on the Project Planned Date | As Late as Possible |
Completion Date | Today | Start No Later Than |