Access requirements

Expand to view access requirements for the functionality in this article.

You must have the following access to perform the steps in this article:

Adobe Workfront planAny
Adobe Workfront license

New: Standard

OR

Current: Plan

Access level configurationsEdit access to Tasks and Projects
Object permissionsManage permissions to the tasks and the project

For more detail about the information in this table, see Access requirements in Workfront documentation.

Enforce a predecessor at the task level

  1. Go to the successor task whose predecessor you want to enforce.

  2. Click Predecessors in the left panel, then click Add Predecessor. You might need to click Show More, then Predecessors.

  3. (Conditional) If you want to add a cross-project predecessor, remove the name of the project in the Parent Project field and replace it with another project.

  4. Specify the name of the predecessor task or tasks in the Tasks field.

  5. Specify the Dependency Type between these two tasks.

    The default Dependency Type is Finish-Start.

  6. Select the Enforced field to enforce the predecessor.

  7. Click Save.