Access requirements
Expand to view access requirements for the functionality in this article.
You must have the following access to perform the steps in this article:
For more detail about the information in this table, see Access requirements in Workfront documentation.
Enforce a predecessor at the task level
-
Go to the successor task whose predecessor you want to enforce.
-
Click Predecessors in the left panel, then click Add Predecessor. You might need to click Show More, then Predecessors.
-
(Conditional) If you want to add a cross-project predecessor, remove the name of the project in the Parent Project field and replace it with another project.
-
Specify the name of the predecessor task or tasks in the Tasks field.
-
Specify the Dependency Type between these two tasks.
The default Dependency Type is Finish-Start.
-
Select the Enforced field to enforce the predecessor.
-
Click Save.