Create predecessor relationships
To create predecessors, see any of the following articles:
- To establish predecessors using the Predecessors tab of the task, see Create a predecessor relationship using the Predecessors area.
- To establish predecessors in a task list, see Create a predecessor relationship on the task list.
- To establish predecessor relationships by chaining tasks, see Create predecessor relationships by chaining tasks.
- To establish cross-project predecessors, see Create cross-project predecessors.
Locate the predecessors of a task
To find the predecessors of a task do one of the following:
-
Go to the project you are working on and do the following:
-
Find the task for which you want to find the predecessors and click the task.
-
Click Predecessors in the left panel.
-
The name of the project that the predecessor is on shows in the Project column.
The number in the # column shows the predecessor task number. For example “6” means the sixth task in the project.
-
-
Go to the project you are working on and do the following:
-
Click the Tasks tab.
-
Choose the Standard View at the top of the task list.
-
The Predecessors column shows the predecessor task numbers.
For a cross-project predecessor, the Predecessors column shows the reference number of the project the predecessor belongs to and the number of the task, separated by a colon.
The predecessor icon turns green when the predecessor task is marked complete. This signals that the dependent task is ready for work.
Hover over this value to get more information on the predecessor, the project, and the dates.
-