Create predecessor relationships

To create predecessors, see any of the following articles:

Locate the predecessors of a task

To find the predecessors of a task do one of the following:

  • Go to the project you are working on and do the following:

    1. Find the task for which you want to find the predecessors and click the task.

    2. Click Predecessors in the left panel.

    3. The name of the project that the predecessor is on shows in the Project column.

      The number in the # column shows the predecessor task number. For example “6” means the sixth task in the project.

      Predecessors section of task

  • Go to the project you are working on and do the following:

    1. Click the Tasks tab.

    2. Choose the Standard View at the top of the task list.

    3. The Predecessors column shows the predecessor task numbers.

      For a cross-project predecessor, the Predecessors column shows the reference number of the project the predecessor belongs to and the number of the task, separated by a colon.

      The predecessor icon turns green when the predecessor task is marked complete. This signals that the dependent task is ready for work.

      Hover over this value to get more information on the predecessor, the project, and the dates.

      Predecessor details