Display information in the Resource Planner by Cost

By default, the availability and allocation information is displayed in Hours in the Resource Planner.

To display Available, Planned, and Budgeted information by Cost in the Resource Planner:

  1. Click the Main Menu icon Main Menu in the upper-right corner of Adobe Workfront, or (if available), click the Main Menu icon Main Menu in the upper-left corner, then click Resourcing.

  2. Go to the Resource Planner.

  3. (Conditional) Select View by Project or View by Role.
    By default View by Project is selected.
    The allocation and availability information displays in Hours.

  4. From the Hours drop-down menu, select Cost.

    If you do not have access to Financial Data in your access level, this option is not available.
    If projects have a different currency than the system currency the Cost for these projects displays in the Resource Planner converted in the currency of the system. Your system administrator defines the system currency.
    For more information about setting up the system currency in Workfront and conversion rates, see Set up exchange rates.
    costs_in_the_planner_with_no_budgeting.png

Calculate Available Cost in the Resource Planner

To display Available Cost values in the Resource Planner you must have the following:

  • Cost per Hour rates for the users and roles

  • Information about user availability.

    Obtaining information about user availability depends on how your Workfront administrator configures the Resource Management Preferences.
    For more information about calculating user availability and setting Resource Management Preferences, see Configure Resource Management preferences.

The following table illustrates how Available Cost is calculated in the Resource Planner:

Available CostCalculation
User Available Cost

The Available Cost per user is calculated using the following formula:

Available User Cost = User Available Hours * User Cost per Hour Rate

NOTE

If the user does not have a Cost per Hour rate in their profile, the Cost per Hour rate of the job role under which they are listed is used in the calculation. If the user has no role associated with them, the Available User Cost is $0.

Role Available Cost

The Available Cost per role is calculated using the following formula:

Available Role Cost = Role Available Hours * Role Cost per Hour Rate

NOTE

If the role does not have a Cost per Hour rate, the Available Role Cost is $0.

Project Available Cost

The Available Cost per project is calculated using the following formula:

Available Project Cost = SUM(User Available Hours * User Cost per Hour Rate)

Calculate Planned Cost in the Resource Planner

Although you cannot view task information in the Resource Planner, the Planned Costs for users, roles, and the projects are calculated by taking into account the following task information:

  • The type of assignment on the task.
    You can leave a task unassigned, or assign the following entities to a task:

    • A User (with or without a Job Role)
    • A Role
    • A Team
      A task assigned to a Team is considered unassigned, from the perspective of the Resource Planner.
  • The Cost Type of the tasks on the project.
    For more information about the Cost Type of a task, see Track costs.

  • The effective dates of the cost rates for job roles and users.

    For example, if the role or user has 10 planned hours in February and 10 planned hours in March, but the cost rate has changed from $12 to $20 in March, the value for the Planned Cost in February is $120, and in March the Planned Cost is $200.

NOTE
User Planned Costs do not influence the Project Planned Cost. Only the Role Planned costs affect the Project Planned Costs, in the Resource Planner.

The following scenarios exist when calculating the Planned Cost for users, roles, and the project:

  • When the Cost Type is **User Hourly **and there is no assignment on the task:

    • Role and user Planned Cost:

      The Role and User Planned Costs are $0.00.

    • Project Planned Cost:

      The Project Planned Cost is $0.00.

  • When the Cost Type is User Hourly and there is a user assignment on the task:

    • Role and user Planned Cost:

      The User Planned Cost is calculated using the following formula:

      User Planned Cost Rate = User Planned Hours * User Cost per Hour Rate

      If a user has a cost rate in their profile, then that rate is used to calculate Planned Cost. Otherwise, the system-level Cost per Hour rate of their Primary Role is used.

      NOTE
      The user can be assigned to the task with one of their secondary job roles, but the rate of the primary job role is used here instead.

      The Role Planned Cost is calculated using the following formula:

      Role Planned Cost = SUM(User Planned Cost)

    • Project Planned Cost:

      The Project Planned Cost is $0.00.

  • When the Cost Type is User Hourly and there is a job role assignment on the task:

    • Role and user Planned Cost:

      The User Planned Cost is $0.00.

      The Role Planned Cost is calculated using the following formula:

      Role Planned Cost = Role Planned Hours * Role Cost per Hours

      The system-level Cost per Hour rate of the job role assigned to the task is used to calculate Planned Cost.

    • Project Planned Cost:

      The Project Planned Cost is $0.00.

  • When the Cost Type is Role Hourly and there is no assignment on the task:

    • Role and user Planned Cost:

      The Role and User Planned Costs are $0.00.

    • Project Planned Cost:

      The Project Planned Cost is $0.00.

  • When the Cost Type is Role Hourly and there is a user assignment on the task:

    • Role and user Planned Cost:

      The User Planned Cost is $0.00.

      The Role Planned Cost is calculated by the following formula:

      Role Planned Cost = Role Planned Hours * Role Cost per Hours

      Workfront looks at the job role that the user fulfills on the task to calculate the Planned Cost for the role.

      If the user is not associated with any role on the task, the Planned Cost is $0.00.

    • Project Planned Cost:

      The Project Planned Cost is calculated using the following formula:

      Project Planned Cost = SUM(Role Planned Costs)

  • When the Cost Type is Role Hourly and there is a job role assignment on the task:

    • Role and user Planned Cost:

      The User Planned Cost is $0.00.

      The Role Planned Cost is calculated by the following formula:

      Role Planned Cost = Role Planned Hours * Role Cost per Hours

      Workfront looks at the job role that the user fulfills on the task to calculate the Planned Cost for the role.

    • Project Planned Cost:

      The Project Planned Cost is calculated using the following formula:

      Project Planned Cost = SUM(Role Planned Costs)

Calculate Budgeted Cost in the Resource Planner

To display Budgeted Cost values in the Resource Planner you must have the following:

  • Budgeted Hours for roles, users, and projects.
  • Cost per Hour rates for users and roles.
NOTE
The Budgeted Hours for the projects are calculated based on the Budgeted Hours for the Roles, not those of users.

The following table illustrates how Budgeted Cost is calculated in the Resource Planner:

Budgeted CostCalculation
User Budgeted Cost

The Budgeted Cost per user is calculated using the following formula:

Budgeted User Cost = User Budgeted Hours * User Cost per Hour Rate

NOTE

If the user does not have a Cost per Hour rate in their profile, the Budgeted User Cost is $0.00.

Role Budgeted Cost

The Role Budgeted Cost is calculated using the following formula:

Role Budgeted Cost = Role Budgeted Hours * Role Cost per Hour Rate

NOTE

If the role does not have a Cost per Hour rate, the Budgeted Role Cost is $0.00.

Project Budgeted Cost

The Budgeted Cost per project is calculated using the following formula:

Project Budgeted Cost = SUM(Role Budgeted Cost).

Previous pageOverview of calculating hours and FTE for users and roles in the Resource Planner
Next pagePrioritize projects in the Resource Planner

Workfront


Learn: Automating Workflows with Workfront Fusion - Unique Use Cases in Action

Workfront

Tuesday, Mar 4, 6:00 PM UTC

Looking for creative ways to use Workfront Fusion to solve business challenges? Join Pan Shahbazian of Starbucks as she shares three unique use cases that can transform your workflows.

Register

The Perfect Blend: A New Era of Collaboration with AEM and Workfront

Adobe Customer Success Webinars

Wednesday, Apr 2, 5:00 PM UTC

Explore how Adobe Experience Manager and Workfront integrate to help teams move from ideation to delivery without the usual bottlenecks, ensuring content is organized, on-brand, and ready to go live faster.

Register

The Future of Adobe Workfront

Online | Session | General Audience

Join Adobe Workfront product leaders to get a sneak peek of the future of strategic planning and workflow in what is the most attended...

Tue, Mar 18, 3:30 PM PDT (10:30 PM UTC)

Register

B2B Reimagined: Transforming Go-to-Market Strategies for Profitable Growth

Online | Strategy Keynote | General Audience

B2B brands are facing a digital revolution. Buyers expect hyper-relevant content and self-service, while internally AI is transforming...

Wed, Mar 19, 1:00 PM PDT (8:00 PM UTC)

Register

Connect with Experience League at Summit!

Get front-row access to top sessions, hands-on activities, and networking—wherever you are!

Learn more

Register to learn something new

WORKFRONT

Join Adobe product experts in live events where you will learn Adobe Workfront best practices, tips and tricks, and hear about the latest product features and updates.

Register