Resize and collapse the burndown chart

You can resize or collapse the burndown chart to adjust how much room it occupies on the story board.

Any changes you make to the size or visibility of the burndown chart are visible only to you, and are reset when you clear your browser cache.

Access requirements

You must have the following access to perform the steps in this article:

Adobe Workfront plan*
Any
Adobe Workfront license*
Review or higher

*To find out what plan or license type you have, contact your Workfront administrator.

Resize the burndown chart

  1. Click the Main Menu icon in the upper-right corner of Adobe Workfront, then click Teams.

  2. (Optional) Click the Switch team icon Switch team icon , then either select a new Scrum team from the drop-down menu or search for a team in the search bar.

  3. Go to the iteration that contains the burndown chart you want to resize.

  4. Hover over the bottom line of the burndown chart, then drag the chart to the desired size.

Collapse the burndown chart

  1. Click the Main Menu icon in the upper-right corner of Adobe Workfront, then click Teams.

  2. (Optional) Click the Switch team icon Switch team icon , then either select a new Scrum team from the drop-down menu or search for a team in the search bar.

  3. Go to the iteration that contains the burndown chart you want to collapse.

  4. Click the arrow icon in the left of the Percent Complete status bar.