Use flags on stories on the Kanban board
On the Kanban board, flags provide a visual indication of when a story is ready to move to the next status. This enables Kanban teams to use a “pull” approach rather than a “push” approach when moving stories across statuses.
Example: Consider the following example of a team using a “pull” approach: Olivia, the graphic designer on the team, finishes her work and then sets the story flag as “Ready to Pull.” This flag provides a visual indication to Tony, the copywriter on the team, that the story is ready for him to move to the next status. Tony then moves the story to the next status when he is ready to begin working on it.
Consider the following when using flags on stories:
-
Flags are not a status, but rather a visual indication that the story is ready to be moved to the next status by another member of the team.
-
Flags do not appear on any story cards that are in the Backlog column or in the Complete column (or in any column where the status of the column equates with Complete).
For more information about story statuses, see Use flags on stories on the Kanban board
Access requirements
You must have the following access to perform the steps in this article:
table 0-row-2 1-row-2 layout-auto html-authored no-header | |
---|---|
Adobe Workfront plan | Any |
Adobe Workfront license |
New: Standard or Current: Work or higher |
For more detail about the information in this table, see Access requirements in Workfront documentation.
Use flags on stories on the Kanban board
To change a flag on a story:
-
Click the Main Menu icon in the upper-right corner of Adobe Workfront, or (if available), click the Main Menu icon in the upper-left corner, then click Teams.
-
(Optional) Click the Switch team icon , then either select a new Kanban team from the drop-down menu or search for a team in the search bar.
-
Go to the Kanban board where you want to change a flag on a story.
-
Expand the story tile to view the flag.
The flag is set to On Track for each story by default.
-
Click the current flag, then select from the following flag options:
-
On Track: The story is in the appropriate status and no action needs to be taken at this time.
This is the default flag for each story on the Kanban board.
-
Is Blocked: The story cannot proceed to the next status. When this flag is set on a story, the story does not count toward the WIP limit. (For more information about WIP limits, see the article Configure Kanban.)
-
Ready to Pull: The story is ready to be moved to the next status by another member of the team.
-