Manually set the Planned Completion Date of a project

You must manually set the Planned Completion Date of a project when you schedule the project from Completion Date.

NOTE
When you manually set the Planned Completion Date of a project, Workfront automatically calculates the Planned Start Date of the project based on the Duration of all the tasks.

To schedule a project from Completion Date:

  1. Click the Main Menu icon in the upper-right corner, then click Projects.

  2. Click New Project then New Project.

    For more information about creating projects, see the article Create a project.

  3. Select Project Details in the left panel, then click the Edit Project icon in the upper-right corner.

  4. In the Schedule Mode field, select Completion Date.

  5. Specify the Planned Completion Date of the project.

  6. Click Save Changes.

    As you start adding tasks to your project, the Planned Start Date of the project calculates based on the total Duration of all of the tasks.

Automatically set the Planned Completion Date of a project

The Planned Completion Date of a project is automatically calculated by Workfront when you schedule the project from Start Date.

To schedule a project from Start Date:

  1. Click the Main Menu icon in the upper-right corner, then click Projects.

  2. Click  New Project then New Project.

    For more information about creating projects, see the article Create a project.

  3. Select Project Details in the left panel, then click the Edit Project icon in the upper-right corner.

  4. In the Schedule Mode field, select Start Date.

  5. Specify the Planned Start Date of the project.

  6. Click Save Changes.

    As you start adding tasks to your project, the Planned Completion Date of the project calculates based on the total Duration of all of the tasks.

    For more information about Task Duration, see the article Overview of Task Duration and Duration Type.

    The Planned Completion Date of the project coincides, in this case, with the Planned Completion Date of the last task on the project.