Manually set the Planned Completion Date of a project

You must manually set the Planned Completion Date of a project when you schedule the project from Completion Date.

NOTE
When you manually set the Planned Completion Date of a project, Workfront automatically calculates the Planned Start Date of the project based on the Duration of all the tasks.

To schedule a project from Completion Date:

  1. Click the Main Menu icon Main Menu in the upper-right corner of Adobe Workfront, or (if available), click the Main Menu icon Main Menu in the upper-left corner, then click Projects.

  2. Click  New Project, then select New Project from the drop-down that appears.

    For more information about creating projects, see the article Create a project.

  3. Select Project Details in the left panel.

  4. Click the Edit Project icon Edit icon in the upper-right corner and then select Overview in the drop-down that appears.

  5. In the Project dates section, click the Schedule Mode field, then select Completion Date.

  6. Specify the Planned Completion Date of the project.

  7. Click Save Changes.

    As you start adding tasks to your project, the Planned Start Date of the project calculates based on the total Duration of all of the tasks.