D - F

Object NameDescription
Dashboards

You can add this field in a report or a view of the Report object, to display the dashboards on which the report is listed in a list.

You can use this field to filter for reports that are listed on a specific dashboard, as well.

For more information about including dashboard information on report object reports, see the "Understanding What Reports Are Listed on Dashboards" section in the article Access and organize reports

Data TypeSee "Custom Data Type".
Days Late

This field shows a date difference between Planned Start and Today if the Actual Completion Date is missing.

Also shows a date difference between Actual Completion and Planned Completion, when an Actual Completion Date is present.

Default Schedule

Customizable default working hours to be assigned to users and projects within an organization.

Schedules are used to calculate the planned, start, and completion dates of tasks that are assigned to users.

DeliverableQuantifiable goods or services that must be provided upon the completion of a project.
Demand ManagementScoring and prioritization of the intake processes.
Department GoalsGoals unique to a specific department that focus on improving operational metrics within the department.
DependencyThe link between two tasks that require one task to change status before the other task can also change status.
Dependency Type

The type of scheduling relationship between a task and its predecessor(s). One example is Finish-Start, which requires that the fist task must Finish before the second task can Start.

For more information, see Overview of task dependency types.

DocumentAny file that is attached to an object within Workfront.
Document Version

Each time the same document is uploaded to the same object, it is assigned a version number. Users can view and change several options for a previous version of a document.

For more information, see Manage document versions.

Due Date

The date when a task or an issue is due to complete. The Due Date of a task or issue is the same date as the Planned Completion Date.

The task and issue Due Date is visible in task and issue lists and reports.

Also see Planned Completion Date in this table.

Duration

The window of time allocated for completion of a task issue, or project (as determined by the number of days between the Planned Start and the Planned Completion).

  • For tasks, the Duration is an editable field if the Duration Type of the task is not Simple. If the Duration Type of the task is Simple, or if the Task Constraint is Fixed Dates, the Duration is a calculation performed by Workfront.
  • For issues, the Duration is always an editable field and it should represent an estimate of a number of days that would require the issue to be resolved.
  • For projects, the Duration is a calculation performed by Workfront and it represents the difference in days between the Planned Start of the earliest task and the Planned Completion of the latest task on the project.

For more information about the difference between Duration and Planned Duration for tasks, see the article Difference between Planned Duration and Duration for tasks.

Duration in MinutesThis field displays the same information as the Duration field in minutes instead of days.
Duration per Occurrence

This displays in the Task Details and the Edit Task boxes of a parent of recurring tasks. It displays the duration of each recurring task. For information about creating recurring tasks, see Create recurring tasks.

Durations modified in individual recurring tasks do not display the value indicated in this field.

Duration Type

A task field that indicates how the work required to complete the task is allocated to the assignees across the task duration. It represents the relationship between the Duration of the task, the Work Required, and the amount of time, or Allocation, the assigned resources should spend on the task to complete it.

This field appears on the Details tab of a task.

The options for the Duration Type of a task are:

  • Calculated assignment
  • Calculated Work
  • Effort Driven
  • Simple

For more information, see Overview of Task Duration and Duration Type.

-->

Duration UnitThe unit that is used to measure time in a power search.
Effort DrivenThe relationship between the number of users and the amount of time the task will take to complete. As you add more users, the total time scheduled for the task to complete decreases, but the duration of the task stays the same. For example if a task is shelling a barrel of peanuts, adding more people will decrease the time scheduled, but the duration in person-days will remain the same.
Elapsed Time

Elapsed time is a unit of time for a task's Duration. It is the time between the Planned Start Date and the Planned Completion Date of a task that includes holidays, weekends, and time off. In other words, elapsed time is the passage of calendar days.

Workfront supports the following elapsed time units for task duration:

  • Elapsed Minutes

  • Elapsed Hours

  • Elapsed Days

  • Elapsed Weeks

  • Elapsed Months

For more information about task duration, including elapsed time, see Overview of Task Duration and Duration Type.

End DateIn a Rate report, this is the date when a new billing rate for a job role at the project level ends. The hours associated with the project that are before this date are multiplied by this billing rate to calculate the revenue on the project.
EngagementThe Work Performance Indicator (WPI) that indicates when commitment and belief in the task, project, team, or organization is waning. This indicates that you need to act to revive that belief and commitment. WPI would be measured by asking the simple questions, "Did you understand what was expected of you? Did the work you were assigned make a difference to the organization? Did you do great work?"
Enterprise GoalsCross-functional goals that contribute to the metrics of the company goals.
EventAny change in a project or task.
Event HandlerAutomated tasks that occur when Events take place. A common example is an automated email notification.
Event notificationEmail that is generated from an event handler.
ExpensesA non-labor cost on tasks or projects.
External

Typically, this is a license type, or a user with such a license. A user with such a license type only has the ability to review information in the system. They cannot actively participate in work.

For more information, see Adobe Workfront licenses overview.

External SystemAny services or software that is stored and governed outside the designated system of record.
Field

Any Workfront object or the information associated with it, as it appears in the database.

For example, "project", "user", "hour" are both Workfront objects as well as fields. "Name", "status", "owner", "start date" are Workfront fields that are associated with the above objects.

When referring to objects, the terms "objects" and "fields" can be used interchangeably.

In the scope of reporting, the "fields" refer to the objects or the information about the object that you want to capture in the report.

NOTE

In text-more reporting, fields refer to the objects or their information as it appears in the database.

Sometimes the name that you see in the user interface is different from the name of the field in the database. For example, "issue" is the name of the object in the Workfront interface, but "opTask" is the name of the object (or the field) in the Workfront database.

It's important to use the field as it appears in the database when writing a text-mode report, view, filter, or grouping, or when creating a calculated field.

For more information, see API Explorer and Text Mode overview.

By default, Workfront comes with a set of fields that define both objects and their information. You can also create custom fields to define objects, but you cannot create custom objects.

In Workfront Planning, you can create custom fields for all record type. Workfront record types come with a very limited number of fields. You must create all fields from scratch and associate them with record types. For information, see Field overview.

Workfront Planning requires an additional license.

Filter

One of the main building blocks of a report or a list element that defines what information displays on the screen. For more information about reporting elements, see Reporting elements: filters, views, and groupings.

The Filter determines the results that display in a report or on an Workfront panel listing, like projects, tasks, or issues.

Financial Work ManagementProcess to manage labor costs, expenses, and revenue data in Workfront.
Fixed CostYou can define a fixed amount of cost for a project. This is part of the Planned Cost of the project which represents the amount of money that you need to complete the project. For information about costs, see Track costs.
Fixed RevenueYou can define a fixed amount of revenue for a project. This is part of the Planned Revenue of the project which represents the amount of money that you might obtain if you complete the project. For information about revenue, see Overview of Billing and Revenue.
Flags

This is the same field as Status Icons, but it is only available for the following views:

  • Templates
  • Expenses

For more information, see the article Built-in Status Icons in Views.

FolderFolders are used to organize documents or reports associated with an object.
FTE (Full Time Equivalent)

This is the Full Time Equivalent which indicates the amount of time that a resource is available for work. The FTE field displays in the following areas:

  • User's profile, when editing or creating the user
  • Resource Planner
  • Scenario Planner (requires additional license for the Workfront Scenario Planner)
  • User lists and reports

The FTE must be a decimal number up to 1, and it cannot be 0.

An FTE of 1 (which is the default for a user's FTE field, as defined in their profile) means that a resource (user or role) works the entire number of hours, based on the schedule that calculates their availability.

Your Workfront administrator decides which schedule to use in determining user's availability.

  • When the Default Schedule is used, Workfront uses the FTE of the user found in their profile to calculate availability.
  • When the User's Schedule is used, Workfront uses the user's time off, Work Time value, and Default Schedule's hours to calculate the user's FTE.

For more information, see Configure Resource Management preferences.

For more information about creating schedules in Workfront, see Create a schedule.

NOTE

For all calculations in the Scenario Planner, Workfront uses the following value: 1 FTE = 8 Hours.

For more information, see Get started with the Scenario Planner.

G - I

Object NameDescription
Gantt ChartA visual timeline of the project dates in a calendar view based on the planned or projected dates as the tasks of the project are currently scheduled.
Goal

There are two concepts of goals in Workfront:

  • Project goals: A set of business objectives agreed to by the relevant stakeholders of a project. Project goals are part of the Business Case of a project.

    You cannot display project goals in lists or reports but you can access them through the API.

    For information about Business Case project goals, see Create Business Case goals.

  • Strategic goals: A strategic goal is an objective that you create to plan your work strategy for a specific time-period. You can create these types of goals using Workfront Goals. Your organization must purchase an additional license and you must have access to this feature to be able to create strategic goals. Workfront Goals are available only with an additional license.

    For more information, see Adobe Workfront Goals overview.

    You can display strategic goals in a goal or a project report and access them through the API.

Goal Hierarchy

In Goal and Project reports, this is a collection field that displays the goals in the hierarchy that a strategic goal belongs to when it aligns to other goals. The goals are separated by a ▸ delimiter.

Only the parents of the goal and the goal display in this field. Children goals do not display.

For information about aligning goals in Workfront Goals, see Goal alignment overview in Workfront Goals.

This field is visible only if your organization has purchased Workfront Goals. For information about managing strategic goals using Workfront Goals, see Adobe Workfront Goals overview.

Goal Success ScoreIn a Project report this field used to refer to project-level goals associated with the Business Case. Currently, this is a deprecated field and is not associated with any functionality.
Goals

In a Project report, this is a collection field that displays all the strategic goals that are associated with a project. The goals are separated by commas.

This field is visible only if your organization has purchased Workfront Goals. For information about managing strategic goals using Workfront Goals, see Workfront Goals overview. For more information about strategic goals and project goals in Workfront, see "Goal" in this article.

Global Interface PreferencesInterface settings that affect all users. Global Interface Preferences can be overwritten by the User Interface Preferences.
Group

A collection of users (possibly from the same department or business unit) that have access to the same objects. In addition to users, groups can be associated with portfolios, programs, projects, project templates, companies, teams, schedules, layout templates, and timesheet profiles.

You can also grant permissions to objects by group. For more information, see Groups overview.

In a list or report of objects of one of the following types, you can use the Group field to list which objects of that type are associated with a particular group: user, portfolio, program, project, project template, company, team, schedule, layout template or timesheet profile.

Group Administrator

Users who manage the objects, access, and users of designated user groups.

In a Group report, this field displays the names of the users designated as Group Administrators in the Group. For more information about Group Administrators, see Group administrators.

Group with Administration Access

In a Layout Template, Timesheet Profile, or Schedule report, this field displays the Groups whose Group Administrators have access to modify the template. You can also filter this report by this field.

For more information, see Create and manage layout templates.

Grouping

A reporting element used to categorize information in a list by a common criterion.

For more information, see the "Groupings" section in the article Reporting elements: filters, views, and groupings.

Handoff DateThe date when a task becomes available for work. The Handoff Date is a calculation and cannot be set manually.
For more information about the Handoff Date, see the article Task Handoff Date overview.
Help DeskAn alternative name to describe the Requests area of Workfront. You can use the Requests area to process customer support tickets, project requests, help desk tickets, etc.
OwnerIn an Hour report, the Owner is the user to whom the hours are attributed. This is different from the user who is actually logging the time. These two entities can sometimes be two different users.
For more information about logging time for another user, see the article Log time.
Hour Status

An attribute set by Workfront for the Actual Hours that users log for tasks, issues, or projects.

Hour entries can have one of the following statuses in Workfront:

  • Submitted: the hours have been logged on a project, task, or issue. They are either part of a billing record or not added to a billing record yet.
  • Approved: the hours have been logged and they have been approved by the Project Owner. They are either part of a billing record or not added to a billing record yet.
  • Not Approved: the hours have been logged and rejected by the Project Owner. They are either part of a billing record or not added to a billing record yet.
  • Billed: the hours have been logged, added to a billing record, and the billing record status has been marked as Billed. They did not require to be approved by the Project Owner.
  • Billed and Approved: the hours have been logged, approved by the Project Owner, and the billing record status has been marked as Billed.

When hours are part of a billing record, the Hour Status indicates whether the hours have been approved or if the Billing Record they belong to has been billed. The Hour Status of an hour entry is only visible in an hour list or report.

For more information about adding hours to billing records, see the section "Add Hours to billing records" in the article Create billing records.

For more information about approving time on projects, see Require time to be approved for a project.

TIP

General Hours that are not logged directly on work items do not display an Hour Status.

Hour Type

An attribute that can be set for Actual Hours that users log for tasks, issues, or projects. This is also an attribute for the hours logged that are not directly linked to work, such as Vacation and Time Off.

For more information, see Manage hour types.

ID

The ID is an alphanumeric indicator associated with every object in Workfront. It uniquely identifies each object in the Workfront database. You can view the ID of any object in a report or a list for each object.

TIP

You can also view the ID in the URL of the object's page. For example, the ID of a project might look something like the number outlined in the following URL, when you access the Project Details page:

https://<your domain>.my.workfront.com/project/5e29c8010027d8eb334762d4fff3ffca/overview

Individual GoalsIndividual goals which contribute to the metrics of the team goals, but not related to personal or career development.
Inherited AccessSharing function that allows access to propagate from object to another. For example, project user's inherit access defined in program and portfolio records.
Initiative

In the Workfront Scenario Planner, you can divide a plan into several initiatives to make it easier to manage the plan. You can build an Initiative report and you can access Initiative information in a Project report.

The Scenario Planner requires an additional license. For information about the Workfront Scenario Planner, see The Scenario Planner overview.

The Initiative report is not visible in your Workfront instance unless your company has purchased a Workfront Scenario Planner license. You cannot access Initiatives through the API.

Initiative Job Role

The Initiative Job Role report type displays information about the job roles associated with a plan initiative in the Workfront Scenario Planner.

The Scenario Planner requires an additional license. For information about the Workfront Scenario Planner, see The Scenario Planner overview.

This report type is not visible in your Workfront instance unless your company has purchased a Workfront Scenario Planner license.

Initiative Job Role Hours

In an Initiative Job Role report, this displays the number of hours associated with a job role in an initiative.

The Scenario Planner requires an additional license. For information about the Workfront Scenario Planner, see The Scenario Planner overview.

This field and the Initiative Job Role report type are not visible in your Workfront instance unless your company has purchased a Workfront Scenario Planner license.

Initiative Job Role Count

In an Initiative Job Role report, this displays the number of specific job roles associated with an initiative.

The Scenario Planner requires an additional license. For information about the Workfront Scenario Planner, see The Scenario Planner overview.

This field and the Initiative Job Role report type are not visible in your Workfront instance unless your company has purchased a Workfront Scenario Planner license.

Initiative Last Published Date

A field in an Initiative, Initiative Job Role, and Project report that displays the date that a plan initiative was last published to a project. You can publish initiatives to create projects or to update projects linked to the initiatives.

The Scenario Planner requires an additional license. For information about the Workfront Scenario Planner, see The Scenario Planner overview.

For information about publishing initiatives, seePublish scenarios to create and update projects in the Workfront Scenario Planner. This field is not visible in your Workfront instance unless your company has purchased a Workfront Scenario Planner license.

Inline SearchA search performed, in the process of completing a form, to find possible entries for one specific field.
Interface SetupThe area of the application that allows defining Custom Views, Filters, Groupings, List Controls, etc.
Is Company Goal

In goal reports, this displays a "True/ False" value for each strategic goal to indicate whether your organization is assigned to the goal as its owner.

This field is visible only if your organization has purchased Workfront Goals. For information about managing strategic goals using Workfront Goals, see Adobe Workfront Goals overview.

Issue

An unplanned work item that usually indicates that there is a problem preventing the completion of a task or project. It is triaged and evaluated for further work effort consideration

An Issue can also be a Help Desk request. Change Orders, Requests, and Bugs are also Issues.

Issue ManagementThe process and rules governing the definition of issue types and the routing, triage, or traffic process associated with each type.
Issue OwnerThe team or users responsible for triaging and completing an issue.
IterationA period of time in which a team produces a pre-defined set of deliverables.

J - L

Object NameDescription
Job Role

Used to identify a user's day-to-day job functions and responsibilities. Job roles can be assigned to work items to identify the required skill needed to complete a work process without assigning it to a specific user.

A user can have more than one role. Examples include Graphic Designer or Consultant.

For more information, see Create and manage job roles.

Journal Entry

A reportable object that tells you information about system updates for tracked fields that appear in the Updates area of projects, tasks, issues, and other objects.

To learn more, see Report on the Updates area with a Journal Entry report.

Kanban Flag

In a Task Report or Issue Report, the Kanban Flag field displays the flag status that is set on the story on the Kanban board. Possible values are On Track, Ready to Pull, and Is Blocked.

For more information about setting flag status on stories on the Kanban story board, see  the article Use flags on stories on the Kanban board.

KPIsA measurable value that demonstrates how effectively a company is achieving key business objectives.
LagAmount of time that must pass after the predecessor task's Planned Completion Date has passed until the dependent task can begin.
Lag Types

The method of calculating the Lag. It can be:

  • Days (work days)
  • Calendar Days (ignore holidays)
  • Percent
  • Day of Week

For more information, see Lag Types overview.

Large Thumbnail

In a Document list or report, it displays a preview of the document in a thumbnail.

Select Large Thumbnail to view a 400 pixel-wide thumbnail in the report.

The size of the thumbnail adjusts when you modify the width of the column in a list or report.

See also "Thumbnail" in this article.

Last 10 ViewersIn a report list, this field displays the names of up to 10 users who have viewed the report most recently.
For more information about usage information in report lists, see the article View report usage.
Last Condition Note

This field displays the update last entered on an object by the owner of the object, This is the owner's most recent activity or interaction on an object.

The Last Condition Note column is empty if the note text of the last note of an object has been deleted. When a new note is entered on the object, it becomes the last note and it displays again in the column.

Last Finance Update DateIn a project report, this field captures the date and the time when the project finances were last calculated and updated. For information about project finances, see Project finances overview.
Last Note

This field displays the update last entered on an object by any user. This is the most recent activity or interaction on an object.

The Last Note column is empty if the text of the last note of an object has been deleted. When a new note is entered on the object, it becomes the last note and it displays again in the column.

When this field is added to a Task report, any updates left on child objects — such as issues, subtasks, documents, etc. — of the task do not display in this column.

Last Viewed ByIn a report list, this field displays information about the user who viewed the report last.
For more information about usage information in report lists, see the article View report usage.
Last Viewed DateIn a report list, this field displays the date on which the report was displayed last.
For more information about usage information in report lists, see the article View report usage.
Layout TemplateDefined by the System Administrator or Group Administrator to identify the tabs and reports that display in a given user's workspace.
Layout TypeIn conjunction with Custom Views, the Layout Type specifies the type of Custom View. Currently, only List is available. In the future, Detail (the Detail view of an object) may become available.
License TypeThe type of license allocated to an Access Level. It is either Full User, Limited User, or Requester.
License Limit PlanIn a Group view or report, this field shows the maximum number of Plan licenses that can be assigned to users who have the respective group designated as their Home Group.
License Limit WorkIn a Group view or report, this field shows the maximum number of Work licenses that can be assigned to users who have the respective group designated as their Home Group.
Limited UserA License Type that allows creation of an Access Level that contains view-only privileges, with the ability to submit issues, enter notes, and upload documents.
List ControlsA part of Interface Setup that allows linking custom Filters, Views, and Groupings to individual Users or globally to all Users.
Lookup fields

In Workfront Planning, after you establish the connection between two record types and you link individual records together, you can reference the linked records' fields on the record you are connecting from.

For example, if you connect a Campaign record type with a Workfront Project object type, you can display the Budget field of connected projects on the campaign records. The Budget project field is a lookup field from projects on a campaign.

The values of lookup fields are automatically populated on the records they are connected from.

For information, see Connected records overview.

Workfront Planning requires an additional license.

M - O

Object NameDescription
Manual Only

One of a Project's Update Types. This setting allows Project Projected and Planned timelines to be updated only when "Recalculated Timelines" is clicked. Projects set up this way will be ignored during the nightly recalculation process and when the project or tasks in the project are updated.

For more information, see Select the project Update Type.

Me

This refers to the currently logged-in user.

We recommend using this field in a filter to make reports more generic when sharing them with other users. This way, you can build only one report which will display different information depending on who logs in to view it, as the information is always customized for the logged-in user.

Max Users

This is a deprecated field. Any information that this field might display is related to a feature that Workfront has removed and the field cannot be updated.

In previous releases of Workfront, you could update this field when creating or editing a job role. It displayed the total number of users that can be associated with a role on each project. A value of zero allowed for an unlimited number of users that can be assigned on a project.

The field is still visible in some reports and lists, but the information displayed cannot be updated.

MilestoneA marker that you can associate with a task to indicate that a key point in the project has been achieved when the task is completed. You generally can use milestones to show a significant event such as the completion of a phase of the project or a set of critical activities. Milestones are typically associated with parent tasks. You must create the milestones before you can attach them to tasks. For information about milestones, see Create a milestone path and Associate milestones with tasks.
Milestone PathA collection of milestones. Milestone Paths are used on projects to distinguish projects with certain types of Milestones from projects with a different set of Milestones.
Milestone TaskA task flagged to indicate a reportable event to measure.
ModuleA single step within a scenario in Workfront Fusion that performs some function based upon the associated app.
My Primary Role

When this is referenced in filters, this displays either users that have the same Primary Role as the logged-in user, or work items assigned to the Primary Role of the logged-in user.

We recommend using this field in a filter to make reports more generic when sharing them with other users. This way, you can build only one report which will display different information depending on who logs in to view it, as the information is always customized for the logged-in user.

My Home Team

When this is referenced in filters, this field displays either users that belong to the Home Team of the logged-in user, or work items assigned to the Home Team of the logged-in user.

We recommend using this field in a filter to make reports more generic when sharing them with other users. This way, you can build only one report which will display different information depending on who logs in to view it, as the information is always customized for the logged-in user.

Naming conventionAn organization-wide set of rules that use data to create names of projects, tasks, and deliverables.
Native IntegrationAn integration that requires no manual coding or API configuration. Also referred to as an "out-of-the-box" integration.
Navigation MenuThe top-center panel of the application that has links to main areas of Workfront.
New Number ValueIn a Journal Entry report, this displays the updated value of a field that replaces the Old Number Value. For more information, see "Old Number Value" in this article.
Non-Billable Expense

An expense that is not marked as billable to the customer. This can be either a planned expense or an actual expense.

The Planned Non-Billable Expense Cost and Actual Non-Billable Expense Cost fields are available for you to add to views and reports. They do not appear on the project or task details pages.

You can find these fields in the following types of reports:

  • Baseline
  • Template
  • Project (Financial Data)

For more information about marking an expense as billable, see Manage project expenses.

Non Work DayA day that is not allocated to the completion of any assignments. This is usually a vacation day, holiday, or weekend. The term display in the API explorer.
NoteA comment or update made on a Workfront object.
Note TextThis displays the text of an update entered by a user on any object.
Number of Linked Goals

In a Project report, this is the number of strategic goals that are associated with the project. For information about associating projects with strategic goals, see Add projects to goals in Adobe Workfront Goals.

For information about strategic goals, also see "Goal" in this article.

This field is visible only if your organization has purchased Workfront Goals. For information about managing strategic goals using Workfront Goals, see Add projects to goals in Adobe Workfront Goals.

Object

The information you display in Adobe Workfront is represented by objects which are stored in the Workfront database. The objects are what drives the information in Workfront. Some examples of objects are:

  • Portfolios

  • Programs

  • Projects

  • Tasks

  • Issues

  • Documents

  • Dashboards

  • Reports

  • Groups

  • Teams

  • Users

  • Companies

  • Custom forms

  • Custom fields

  • Hours

  • Billing Rates

  • Templates

  • Template tasks

    NOTE

    This is not an extensive list.

For more information, see Understand objects in Adobe Workfront.

Object TypesIf you create a report or list containing all of your custom forms, you can use this field as a view or filter to see which object types are associated with each form.
Old Number ValueIn a Journal Entry report, this displays the original value of a field before it was updated. Once a field's value is updated, it will display as the New Number Value in a Journal Entry report. For more information, also see "New Number Value".
On Change Only

One of the Project Update Types. When this is selected, the Project Projected and Planned timelines update only when an update or change is made to the project or to a task within the project. It does not update the project every night.

For more information, see Select the project Update Type.

Op TaskThe name for Issue in the Workfront database, used in text mode reports or calculated custom data.
OpenAn issue or task that is not complete, but being worked on.
Org ChartShort for Organizational Chart. This is a chart showing the hierarchy of an organization. It is also on the Tab on the User detail screen that displays and allows setting the User's Company and Reporting relationships.
Organizational SetupThis defines Companies, Groups, and Security Profiles for your organization.
Other GroupsIn a report or view that lists users, this field displays all the groups where each user is a member.
Override Currency

In a Job Role report, this is the currency associated with a job role. It is an override of the Base Currency as established in the Setup area by the Workfront administrator.

For more information, see Create and manage job roles.

Override Currency Billing/ Hour

In a Job Role report, this is the billing per hour rate of the job role using the selected Override Currency of the job role.

For more information, see Create and manage job roles.

Override Currency Cost/ Hour

In a Job Role report, this is the cost per hour rate of the job role using the selected Override Currency of the job role.

For more information, see Create and manage job roles.

OwnerThe user responsible for the completion of the designated object.
Owner Type

In a Goal report, this displays the type of owner that is assigned to a strategic goal. The following are the goal owner types:

  • User

  • Team

  • Group

No value displays in this field when the goal owner is your organization.

This requires an additional license. For information about Workfront Goals, see Adobe Workfront Goals overview.

P - R

Object NameDescription
ParameterA parameter is a custom field. You can build a report for all parameters, or custom fields in your system.
ParentIn a report, this field shows information about the parent of the object. For example, in an issue report, it might show information about the task or project that the issue is logged under; in a task report, it might show information about the direct parent task or about the project. For more information about what objects might have parents in Workfront, see the "Interdependency and hierarchy of objects" section in the article Understand objects in Adobe Workfront.
Parent LagThe amount of time that must pass between the Parent Task start and the Subtask Start.
Parent TaskAlso known as a Summary Task. This is a task that has Subtasks (also called Children Tasks). The Duration, Work Required, and Percent Complete of the Parent Task is calculated from the Subtasks.
Part-Time ResourcesA licensed user who has less capacity than the default schedule defined in the system.
Percent Complete

A project, task, or issue field that shows what percentage of the work associated with the task, project, or issue is completed.

You can update this field manually for issues and working tasks.

For projects and parent tasks, this field is a roll-up from all the working tasks and you cannot update it manually.

For more information, see Project Percent Complete overview.

Permission

Rights that are granted to a user on an object, typically given so they can complete work on the item or view the item. You can grant permissions to:

  • Projects
  • Tasks
  • Issues
  • Portfolios
  • Programs
  • Reports
  • Dashboards
  • Documents
  • Custom Forms
  • Views
  • Filters
  • Groupings

For more information, see Overview of sharing permissions on objects.

Plan

This is a full license type in the Workfront system. Users must have this to access all of the features in Workfront.

For more information, see Adobe Workfront licenses overview.

Plan (in the Scenario Planner)

A plan is the main object when working with the Workfront Scenario Planner. You can outline the strategy for your company's near and long-term future and identify each high-level outcome and add it as a plan to the Workfront Scenario Planner.

You cannot display Scenario Planner plans in a report and you cannot access them through the Workfront API.

The Scenario Planner requires an additional license. For information about the Workfront Scenario Planner, see The Scenario Planner overview.

PlannedThe time frame within which something is scheduled to occur. When you create projects, tasks, or issues in Workfront, you establish the planned start and end dates, as well as the planned timeframe during which they occur. These values represent your original intention or estimate of how long an item should take to complete.
Planned BenefitThis is a manual entry for the Project Manager to estimate whether completing a project would bring any monetary benefit to the organization. Specifying this value can be part of putting together a Business Case for the project. You must have Manage permissions to the project to update this value.
Planned Budgeted Hours

In a Budgeted Hour report, this displays the number of hours budgeted for projects or Job Roles in the Resource Planner.

For information about budgeting projects or roles in the Resource Planner, see the article Budget resources in the Resource Planner using the Project and Role views. For information about the Budgeted Hours report, see the article Report: Budgeted Hour.

Planned Completion Date

You can manually set the Planned Completion Date of a task, project, or issue to a date of your choosing. If you do not set the Planned Completion Date, Workfront sets it automatically. When set automatically, the Planned Completion Date is: Planned Start Date + Duration

For more information, see the following articles:

Planned CostA total of the Planned Labor Cost and the Planned Expense Cost of the project. This does not include the Planned Risk Cost on the project.
Planned Date Alignment

This is an automatic indicator that Workfront assigns projects, tasks, and issues to show when an item will be completed in relation to its Planned Completion Date.

The following are possible values for the Planned Date Alignment indicator:

  • Will be done on the planned completion date
  • Will be done before the planned completion date
  • Will be done after the planned completion date

The Planned Date Alignment is visible in project, task, and issue lists and reports.

Planned Duration

A task's Planned Duration is usually the same as the task's Duration. It represents the difference in days between the Planned Start and the Planned Completion Dates of the task.

When the task has a Duration Type of Effort Driven, the Planned Duration can differ from the Duration of the task, based on how many resources you assign to the task.

For example, if a task with a Duration Type of Effort Driven has a Duration of 3 days and you assign one resource with a full-time schedule to the task, the Planned Duration is 3 days, as well. If you assign three resources with a full-time schedule to the same task, the Duration stays 3 days, but the Planned Duration becomes 1 day. The Planned Duration also changes the Planned Start and Planned Completion dates of the task, to reflect the new Planned Duration. As a result, the timeline of the project is affected as well.

For more information about the difference between Duration and Planned Duration for tasks, see the article Difference between Planned Duration and Duration for tasks.

Projects and issues don't have a Planned Duration.

Planned Duration Minutes

The Planned Duration Minutes of a project or an issue is the Duration of the project or issue in minutes.

Tasks don't have a Planned Duration Minutes field.

Template Tasks have a Planned Duration Minutes field which displays the Planned Duration of the task in minutes.

Planned Expense Cost

The sum of the Planned Amounts for all expenses logged for a project or a task.

EXAMPLE

If you create an expense for Task 1 and enter $600.00 in the Planned Amount field, the Planned Expense Cost for this task is $600.00.

For a project, Workfront uses the following formula to calculate Planned Expense Cost:

Project Planned Expense Cost = SUM (All Project Planned Expense Costs) + SUM (All Tasks Planned Expense Costs)

Planned Hours

This field appears in the projects, tasks, and issues areas, reports for projects, tasks, or issues, and resource management tools like the Resource Planner, Workload Balancer and the Utilization report.

It shows the number of hours that the Project Owner estimates that each task or issue should take to complete. For projects, it is generally a roll-up of the Planned Hours from the tasks on the project.

The Planned Hours field might display different information depending on where you view it from. For information about Planned Hours, see Planned Hours overview.

Planned Hours are stored in minutes in the Workfront database. When writing calculations using this field, ensure you account for the fact that the hours display as minutes.

By default, Planned Hours are distributed equally to all the days within the duration of a work item and also equally for all resources assigned to the task. Users can update the daily number of Planned Hours for a work item or the individual Planned Hours for each assignee.

Updating this field differs for projects, tasks, and issues:

  • For issues, you can manually update this field. Issue Planned Hours are not added to the Project Planned Hours.

    TIP

    In an issue report, one of the Planned Hours fields is replaced by the Work field. The field displays the number of Planned Hours on the issue. For more information, see the "work" or "Work" fields in this table.

  • For tasks, you can manually update this field when the Duration Type of the task is Calculated Assignment or Simple. This field is calculated by Workfront when the Duration Type of the task is Calculated Work or Effort Driven.
    For information about Task Duration, see the article Overview of Task Duration and Duration Type.
  • For projects, Workfront calculates the Planned Hours by adding all Planned Hours from all the tasks on the project.

TIP

You can display Planned Hours in project, task, or issues reports also by using text mode and reference additional fields. For more information, see the "work", "Work", and "workRequiredExpression" fields in this table.

Planned Labor Cost

For a task, the hourly rate of the user or role multiplied by the number of hours assigned to the user or role.

For a project, it is a total of all Planned Labor Costs of all the tasks.

Whether the rate of the user or role is used depends on the Cost Type that is selected for the given task.

For more information, see Track costs.

Planned Revenue

Tasks and projects can display a value for Planned Revenue in Workfront. Planned Revenue represents the amount of money associated with the Planned Hours of the tasks on the project. For projects, it can also include the Fixed Revenue of the project.

For tasks, this is the revenue associated with the Planned Hours of tasks. The Planned Hours from all tasks roll up to the Planned Hours of the project to contribute to the calculation of the project Planned Hours.

Workfront calculates Planned Revenue for tasks and projects using the following formulas:

Task Planned Revenue = Planned Hours * Billing hourly rate

Project Planned Revenue = SUM (All tasks Planned Revenue) + Fixed Revenue

The project Planned Revenue that displays in the Project Details area and in project reports differs from the Planned Revenue that displays in the Utilization report.

The Planned Revenue in the Project Details area reflects the task revenue as well as the Fixed Revenue of the project. The Planned Revenue in the Utilization Report displays Planned Revenue associated only with the tasks in the project.

EXAMPLE

If the project has 1 task with 10 hours, assigned to a Consultant with $20 hourly rate, and the project has $100 Fixed Revenue, the Utilization report displays $200 for Planned Revenue (the Planned Revenue associated with the hours on the task). The Project Details section displays $300 (the Planned Revenue from the task and the Fixed Revenue for the project.)

For information about tracking revenue in Workfront see Overview of Billing and Revenue.

For information about Planned Revenue calculations in the Utilization report, see View resource utilization information.

Planned Risk Cost

The total of the Potential Cost of all the risks on the project factoring in their Probability of occurring. This amount is not included in the Planned Cost of the project.

The Planned Risk Cost of a project is calculated by the following formula:

Planned Risk Cost = SUM(Potential Risk Cost * Probability / 100)

Portal ProfileAn administrator-defined collection of Tabs and Sections that displays in Workfront.
Portal SectionOne component of a Tab on a Dashboard or Portal Page. Usually a single Report, Chart, Calendar, or list of key information.
Portal TabA Tab on a Portal or Dashboard that contains up to three Portal Sections.
Portfolio

A collection of projects that have unifying characteristics. Those projects usually compete for the same resources, budget, or time slot. You can divide Portfolios into Programs and associate the projects with the Programs before they are added to a Portfolio.

For more information about portfolios, see Portfolio overview in Adobe Workfront.

Portfolio ManagementA practice area focused on managing a collection or related programs and project efforts.
Portfolio OptimizerA Workfront tool to assist in assessing and prioritizing projects within a portfolio.
Portfolio OwnerThe stakeholder responsible for the prioritization and budget for a portfolio.
Potential Risk CostThis is a project field that you can locate in lists and reports. It shows the potential cost for the risks associated with the project, should they occur. For more information see Calculate Potential Risk Cost.
Predecessor

A task that must be completed prior to the completion of a dependent task. Also a task that is marked as a Dependency for another task. Predecessors allow the planner to set sequence-dependency logic, such as to start a task after another task finishes.

For more information, see Overview of task predecessors.

Primary CompanyThe Company that the user belongs to as designated in their user settings. Companies can also be associated with projects.
Primary Contact

The Primary Contact is the creator of an issue and it is automatically designated by Workfront when the someone creates the issue. You can manually update this field if you have Manage permissions to the issue. An issue can have only one Primary Contact.

If you change the Primary Contact, the user originally designated as the primary contact still has Manage access to the issue.

When converting an issue to a task or a project, the user designated as the Primary Contact of the issue becomes the Converted Issue Originator of the project or task. If the Primary Contact of the issue is updated after the issue was converted, the Converted Issue Originator will be preserved as the Primary Contact of the issue at the moment when the conversion happened. See also "Converted Issue Originator" in this article.

PriorityA value that can be assigned to a task, issue or a project to designate how important it is.
PrivateOn a Note or Document, this option makes that object hidden to most viewers. For a Private Help Request Queue, only users on the Project Team can submit issues to that queue (or project) through the Requests area.
ProfileAll information about a user account.
ProgramA subset within a portfolio, where similar projects can be grouped together in order to achieve a well-defined benefit.
Program ManagementManagement of cross-project dependencies, risks, issues, requirements, and solutions to keep the program healthy and achieve the defined program benefit.
Program OwnerThe stakeholder responsible for supervising and organizing activities to ensure that project goals align with the company objectives.
Progress

In a Goal report, this displays the percent of how close a strategic goal is to completing. The percent of progress displays as a number. For information about strategic goals, also see "Goal" in this table.

This field is visible only if your organization has purchased Workfront Goals. For information about managing strategic goals using Workfront Goals, see Add projects to goals in Adobe Workfront Goals.

Progress Status

In a Project, Task, and Goal report, this field displays the Progress Status of projects, tasks, or strategic goals. For more information, see the following articles:

ProjectA large amount of work that must be completed within a specific timeframe and must use a specific budget and number of resources. To make it manageable, you divide the project into a series of tasks. Completing all the tasks results in the completion of the project. For information about planning a project, see Plan a project overview.
Project Assignment Planned HoursIn an Initiative Job Role report, this displays the number of Planned Hours associated with a job role assigned to tasks or issues in the project. This field and the Initiative Job Role report type do not display in your Workfront instance unless your company has purchased a Workfront Scenario Planner license. For information about the Workfront Scenario Planner, see The Workfront Scenario Planner overview.
Project DetailsThe details of the current status of a Project.
Project Budgeted Cost

This is the Budgeted Cost of a project as it displays in lists and reports.

See also "Budgeted Cost" in this article.

Project ManagementA set of policies that governs the thresholds for project creation, categorization, and naming of the projects.
Project OverheadIn an Hour report, this field is reserved for financial information tied to the hours logged with the hour type of Project Time. Projects can have their own Billing Rates and if an hour is logged directly on a project, then those rates will be used in calculations. Based on the project settings, projects can also have different currencies and there can be a currency conversion for those hours. The Project Overhead object allows Workfront to get that information.
Project OwnerThe user responsible for managing the scope, timeline, and assignments of a project. The default approver for change orders, financial changes, and deliverables.
Project PlanningProcesses to develop and maintain the project schedule.
Project SponsorA designated stakeholder profile that each of your user's should relate to. In Workfront, these are designated as Access Levels
Project Teams

The collection of users or roles assigned to a project

For more information, see Project Team overview.

Project trackingThe data used to measure the health and scope of a project
Projected

An estimate of the timestamp of when the work will be completed based on the planned hours and percentage complete of a task, issue, or project.

This refers to dates or the Duration of tasks, issues, or projects. Usually, it designates dates and durations that are more true to the life of the work items, after some work has already been completed or some time has passed.

For example, the Projected Completion Date of a task is the date when Workfront estimates that the task will complete, based on how much work has been done on it so far, how many people are assigned to it, and how much time has passed since the start date.

Proof DeadlineIn reports that contain the Document Version object (such as a Document Version report and Proof Approval report), This field displays the day of the week, date, time of day, and year of the proof deadline.
Proof DecisionIn reports that contain the Document Version object (such as a Document Version report  and Proof Approval report), this field displays the decision status of the proof (pending, changes required, or approved)
Proof NameIn reports that contain the Document Version object (such as a Document Version report and Proof Approval report), this field displays the proof name.
Proof PagesIn reports that contain the Document Version object (such as a Document Version report and Proof Approval report), this field displays the number of pages included in the proof.
Proof Progress

In reports that contain the Document Version object (such as a Document Version report and Proof Approval report), displays the progress status of the proof (Sent, Opened, Commented, Decision Made).

For more information, see Proof progress overview in Proof progress and status overview.

ProofingA review process where one or more users mark and comment on content that should be changed in an image, a text document, a video, or interactive web content.
PublicOn a Note or Document, this option makes that object accessible to other users, or even people from outside Workfront. For a Help Request Queue, Public means that all users that can submit issues to a project can submit issues through the Requests area.
QualityThe perception of work quality within the organization.
QueueAlso called Help Desk Queue or Help Request Queue. This is a project that has been published to the Requests area to allow users to submit issues to it. Usually queues are created for particular topics, such as Bugs, Project Requests, etc.
Queue PropertiesThese settings define issue submission rules for a project that is being published to the Requests area.
Queue Topic

A property on a Help Request Queue that allows users submitting an issue to select a Topic. Topics can:

  • Be associated with a Custom Data Form.
  • Assign the issue automatically to a user, role, or team through the Routing Rule set on the selected Topic.
  • Move the issue to a different project or queue through the routing rule set on the selected topic.

For more information, see Create Queue Topics.

RankIn an Access Level report, you can manually indicate a Rank of the Access Level. This helps you, as the Workfront administrator, to visually identify the level of complexity associated with each Access Level. For example, you can give lower numbers for more complex (Plan-level) Access Levels, and higher numbers for less complex (Requester-level) Access Levels. You cannot rank the standard Access Levels.
ReadyThis field on a task report indicates whether an Agile task has been marked as Ready on the backlog. This flag only applies to Agile tasks, which are tasks assigned to an Agile team.
Record

In Workfront Planning, a record is a unique instance of a record type.

After adding a record type to a workspace, you can start adding records of that type on the record type's page.

For example, "Campaign" can be a record type and "Summer Campaign for EMEA" is a record of the Campaign record type.

For information about creating records, see Create records.

Workfront Planning requires an additional license.

Record type

The object type of Workfront Planning.

Unlike Workfront, where the object types are predefined, in Workfront Planning, you can create your own object types.Workfront Planning object types are called record types.

For example, in Workfront the object types of Program, Portfolio, Project, Task, or Issue are already created.

In Workfront Planning, you can create any record types that meet your organization's workflows. Later, you can define how the record types relate to one another or form dependencies.

For information about creating record types, see Create record types.

Workfront Planning requires an additional license.

Recurrence FrequencyA field that displays in the Task Details or the Edit Task box of a parent of recurring tasks. It is the frequency with which the tasks in the recurrence occur. For information about creating recurring tasks, see Create recurring tasks.
Reference Number

Projects, tasks, and issues are automatically associated with a unique reference number as they are created. You can view the Reference Number in the Details page of projects, tasks, or issues, or in a list or report.

TIP

You can defer to reference numbers when two items have the same name, as reference numbers are always unique.

Workfront automatically generates sequential reference numberss at the system level. Each project, task, or issue gets the next available number in the sequence.

For example, if User A creates a task, Workfront might automatically assign the task the Reference Number of 100. If User B creates an issue right after this, Workfront assigns the issue the Reference Number of 101. You cannot manually edit Reference Numbers.

Rejection IssueIn a project or a task report, this is the issue that is created when the approval for the project or the task is rejected. For information about rejection issues, see the article Create an approval process for work items.
Relationship types

Workfront objects are always connected to each other using one of the following relationship types:

  • One to many: In this relationship, one object can be connected to multiple other objects of different types. For example one project can have multiple tasks. The Project-Tasks relationship is a one to many relationship. You cannot display this relationship in a report using the Standard interface. You must use text mode reporting to view one to many relationships.
  • One to one: In this relationship, one object can only be connected to one other object of a different type. For example, a project can only have one Group. The Project-Group relationship is a one to one relationship. You can display one to one relationships between objects in a Standard report.
  • Many to one: In this relationship, multiple objects can be connected to only one other objects of a different type. For example multiple tasks can be connected to the same project. The Tasks-Project relationship is a many to one relationship. You can display many to one relationships between objects in a Standard report.
  • Many to many: In this relationship, multiple objects of the same type can be connected to multiple objects of a different type. For example, several users can belong to multiple Other Teams, and the teams can belong to several users. You cannot display this relationship in a report using the Standard interface. You must use text mode reporting to view many to many relationships.
Remaining Risk Cost

A project field that shows the difference between the Planned Risk Cost of a project and the total of all Actual Costs of all risks on the project.

The Remaining Risk Cost for a project is calculated using on the following formula:

Remaining Risk Cost = Project Planned Risk Cost - SUM(Actual Cost for all risks)

ReplanningChanging the dates of a project to repair or overcome problems. For example, a project that has been on hold for several months would need to be replanned to reflect accurate dates. This is a manual operation of adjusting either the dates of the project or those of the tasks.
ReportA chart or table containing information about one given Workfront object and its related attributes.
RequestA type of issue that is triaged in a single centralized queue and is unrelated to an ongoing work effort.
Request QueueThe backlog of issues that is managed by a traffic and triage process.
Request velocityTotal work cycle time to intake and complete a request.
RequesterTypically a license type. A user with a Requester license can submit requests for new work to occur in the system.
Reserved TimeDays specified on a user's Personal Time, indicating that the user will not be available for work. See "Non Work Days".
Resolve Issue

In an issue report, use this field in views or filters to refer to the issue that resolves the issue.

For information about displaying resolving objects in reports, see View Resolvable and Resolving Object information in a report in Overview of Resolving and Resolvable Objects.

Resolve Project

In an issue report, use this field in views or filters to refer to the project that resolves the issue.

For information about displaying resolving objects in reports, see View Resolvable and Resolving Object information in a report in Overview of Resolving and Resolvable Objects.

Resolve Task

In an issue report, use this field in views or filters to refer to the task that resolves the issue.

For information about displaying resolving objects in reports, see View Resolvable and Resolving Object information in a report in Overview of Resolving and Resolvable Objects.

ResourceUsers or roles that exist in Workfront and are assigned to Project Teams, tasks, and issues. They are responsible for completing the work associated with projects, tasks, or issues.
Resource Management

Resource Management is an enterprise set of tools that allows you to accurately forecast the use of your resources based on their availability so that the work that must be done is completed on time and on budget.

With Resource Management tools you can plan long-term capacity and short-term scheduling needs for your resources.

For information about Resource Management in Workfront, see Get started with Resource Management.

Resource Manager IDsIn a project report, you can use this option when creating a filter to find a specific resource manager.
Resource Managers

In a project report or list view, this is an informational field that displays users designated to perform resource management activities on the project. When you use "Resource Managers" in a report, a list of resource managers is displayed, with each resource manager on the project separated by a comma. You can designate up to 30 resource managers on a given project.

For more information, see the article Designate Resource Managers for a project or template.

Resource Planner Budgeted HoursThe hours budgeted for the project and the resources associated with it in the Resource Planner. See also "Budgeted Hours" in this article.
Resource PlannerAn advanced Workfront tool that lets you view and manage resources across projects, job roles, or users. For information, see Resource Planner overview.
Resource Planner Budgeted Labor Cost

These is the cost associated with the hours budgeted for project job roles using the Resource Planner.

See also "Budgeted Labor Cost" in this article.

Resource Pools

Resource Pools are collections of users that can be associated with a project. The users in the same Resource Pool usually belong to the same department, have similar or complementary skills, or are funded by the same budget. You can associate multiple Resource Pools to a project or to a user. A resource pool can be assigned exclusively to a project or shared by several projects.

For more information about resource pools, see Resource pools overview.

In project reports, Resource Pools show all the pools associated with a project. This object cannot be used in a grouping.

Resource UtilizationA Report displaying the number of hours available during a certain time period and the number of hours scheduled for each user in the report. This is also calculated into Average Hours Per Day and an allocation percentage.
ResultIn Workfront Goals, a result is a progress indicator for a goal. It can be a number, a percentage value, or a currency amount that you update manually. You cannot display results in a report and you cannot access them through the Workfront API. For information about activities, see Get started with results and activities in Adobe Workfront Goals.
RevenueA billable amount for the task or project. The amount can be hourly, fixed, or a combination of both.
Revenue TypeRevenue type determines how the task will accrue revenue. Some examples include Fixed Hourly, Role Hourly, and Role Hourly w/Cap. For information about tracking revenue in Workfront see Overview of Billing and Revenue.
ReviewerTypically a license type. A user with a Reviewer license has the ability to review and approve work items in the system.
Risk

This may refer to the following concepts in Workfront:

  • A field on a project that indicates how risky a project can be. You can prioritize the execution of your projects based on the level of risk. Projects can have the following levels of risk:

    - Very Low

    - Low

    - Medium

    - High

    - Very High

    The levels of risks you indicate for a project cannot be customized.

    For information about updating the Risk of a project, see the " Project Settings" section of the article Edit projects. You can display the risk field of a project in reports.

  • An event that might occur during the life of a project that identifies a potential impact to the cost, scope, or schedule of the project. You define potential risks to a project and associate a probability of them occurring or a cost as you build the project's Business Case. For information about adding risks to the Business Case of the project, see "Create and edit risks on projects".

    You cannot display risks defined in the Business Case in reports. You can only display several types of Risk Costs in reports and lists.

Risk Cost

The cost associated with the risks on a project. The following are risk costs associated with projects that you can display in reports:

  • Actual Cost: a field on a risk that shows the actual cost for the risk that has occurred. In addition to reports and lists, you can locate it in the Edit Risk box when editing or creating a risk.

    For project, task, or issue costs, see "Actual Cost" in this article.

  • Planned Risk Cost: a field on the project that shows a total of all Potential Risk Costs for the project. See also "Planned Risk Cost" in this article.

    For information about Potential Risk Cost, see Calculate Potential Risk Cost.

  • Remaining Risk Cost: a field on the project that displays the difference between the total of the Actual Costs of all risks and the Planned Risk Cost. See also "Remaining Risk Cost" in this article.

Risk ManagementProcesses to identify, mitigate, and monitor risk.
RoleSee "Job Role" in this article.
RoutingAutomatically assigning or moving an issue, usually due to a Queue Topic or by way of being the Default Route (Routing Rule) for the queue.
Routing RuleA setting on projects and queue topics that automatically assigns an issue to a user, role, or team, or moves the issue to another project or queue topic. Routing Rules are generally used with Help Request Queues to automatically assign incoming issues.

S - U

Object NameDescription
Saved SearchA search for which the search criteria have been saved. Saved Searches make it easy to run the same each again without having to enter the search criteria again.
Scenario (in Workfront Fusion)

A scenario is comprised of a series of steps (modules) that indicate how data should be transferred and transformed between apps/ services.

For information about scenarios in Workfront Fusion, see Adobe Workfront Fusion scenario overview.

Scenario (in the Workfront Scenario Planner)

In the Scenario Planner, a scenario is a copy of a plan.

The Scenario Planner requires an additional license. For information about the Workfront Scenario Planner, see The Scenario Planner overview.

For information about creating scenarios, see Create and compare plan scenarios in the Scenario Planner.

ScheduleThe weekly work schedule, including working times, combined with Days off (such as Holidays) and exception days (such as a Saturday work day). Yiu can associate schedules with projects and users.
Schedule ExemptionAlso known as a Modified Shift. Days scheduled in contrast to the regular weekly working times as defined by the schedule. For example, a Saturday scheduled to work, when the Schedule is set up to only Work Monday Through Friday, would be a Schedule Exemption.
Scheduled Report

When you build a report of reports, you can display information about the schedules of the report, if the report is scheduled for delivery using the Scheduled Report field. This field shows multiple values, one for each schedule of each report, in a bulleted list. For more information about scheduling reports, see the article Report delivery overview.

Because this field shows multiple values, it cannot be used in a grouping. You can access it only in a filter or a view.

Scope ChangeAn Audit Trail that, if active, generates a note anytime a change is made to the Scope of a project or task, such as if a Task Duration or the Predecessors are changed.
SectionAn area on the screen, with its own header, created to organize the Custom Data for display purposes.
Section BreakA gap or border between sections.
SecurityThe settings that allow a user to interact with certain objects in the system and not others. See also "Access Levels" in this article.
SetupThe area where administrators can set up system configurations and preferences.
Severity

Severity is an indication of how likely an item is to impact the completion of the work. For example, an issue with high Severity may completely block a task's completion, but an issue with low Severity may be merely cosmetic.

For more information, see Update issue severity.

SeveritiesSee "Severity" in this article.
SharingThe action of allowing other Users to view or edit a specific item in Workfront.
Slack DateIn a task view or report, the Slack Date displays the exact date when a task could definitely impact the Completion Date of the project. For information about the Slack Date of a task, see Task Slack Date overview.
Smart Assignments

When assigning tasks or issues to users, Workfront makes recommendations (Smart Assignments) about who the best users are to complete the work, based on the time they have available to complete it and their relationship to the project.

For more information , see Smart assignments overview.

Source

Indicates the parent object of another object. For example, a document attached to a task has the name of the task in the Source field of a Document report or view; an issue logged under a project has the name of the project in the Source field of an Issue report or view.

The following reports display a Source column where you can view information about the parent object:

  • Issue reports
  • Hour reports
  • Document reports

If users don't have permissions to the parent object of an issue, hour, or document, the Source column of the report displays empty, even when the report is configured to display, or to be delivered with the access rights of another user.

In order to show information about the parent object in the report, we recommend adding a column for the parent object where you can display the name of the parent.

For example, you can add any of the following to a report with a Source column:

  • The Project Name, Task Name, or Issue Name columns to a document or hour report.
  • The Project Name or Task Name columns to an issue report.

For more information, see Run and deliver a report with the access rights of another user

Start Date

The Date when the work on an item is set to start. There are several Start Dates in Workfront:

  • Planned
  • Actual
  • Projected

In a Rate report, this is the date when a new billing rate for a job role at the project level starts. The hours associated with the project that are after this date are multiplied by this billing rate to calculate the revenue on the project.

Status

An indicator used to signal a workflow position of a work item or of a strategic goal.

For projects, the Status is a setting on the project that indicates whether the project is:

  • Current
  • On Hold
  • Complete
  • Dead

For more information on a project's Status, see Access the list of system project statuses.

For tasks, the Status is a setting on the task that indicates whether the task is:

  • New
  • In Progress
  • Complete

For more information on task Status, see Access the list of system task statuses

For issues, the Status is a setting on the issue that indicates whether this issue is:

  • New
  • In Progress
  • Awaiting Feedback
  • On Hold
  • Resolved
  • Won't Resolve
  • Cannot Duplicate
  • Verified Complete
  • Reopened

For more information on issue Statuses, see Access the list of system issue statuses.

For strategic goals, the Status is a setting on the goal that indicates whether the goal is:

  • Active
  • Draft
  • Inactive
  • Closed

For more information about strategic goals, also see "Goal" or "Goals" in this article.

For strategic goals, this field is visible only if your organization has purchased Workfront Goals. For information about managing strategic goals using Workfront Goals, see Workfront Goals overview.

Status ChangeAn Audit Trail. A note is generated when a user changes the Status of the project, task, or issue.
Status Icons

You can add the built-in Status Icons field as a column in your views to enhance visibility into key points about your objects, like:

  • An object has documents attached
  • An object is associated with an approval process
  • An object has additional notes associated with it
  • An expense is billable or reimbursable
  • A task is on a critical path
  • A user belongs to a company, a team, or is located in a different time zone

You can add the Status Icons field in the views of the following objects:

  • Tasks
  • Issues
  • Projects
  • Template Tasks
  • Templates
  • Expenses
  • Documents
  • Users

For more information, see Built-in Status Icons in Views.

Status Update

In a project, task, or issue report, this field shows the most recent status update that object owners have provided in the 'Updates' area. For projects, this means that comments made by the Project Owner, and for tasks and issues, this means that comments made by the assignees.

Comments made when updating the status of an object do not display in the Status Update column.

To show the 'New,' 'In Process,' and 'Complete' statuses, use the Status column.

For more information on statuses, see the article Update task status.

StatusesSee "Status" in this article.
StoryboardA chart that represents the status of stories (tasks in the agile methodology) and how they are progressing toward completion.
Story HoursA metric used to measure the difficulty or complexity of a Story. Agile teams can choose whether to use Hours or Points.
Story PointsA metric used to measure the difficulty or complexity of a Story. Agile teams can choose whether to use Hours or Points.
StrategicLong-term work that changes the organization or how the organization works.
Strategic AlignmentMeasuring and aligning company goals across portfolios and programs.
stretch

This is used in report columns when using the Text Mode interface.

The stretch is used to identify which columns occupy extra space not needed by the view. The user interface width of the workspace for a typical user is about 850 pixels. This means that if you have a view with four columns (150 pixels each) that your view occupies 600 of 850 pixels. There are 250 extra pixels in the UI that will be added to the columns that have a stretch percentage provided.

The stretch of a column is enforced when you use the additional line of code: usewidths=true for at least one of the columns in the view.

Subscribers

Users that subscribe to projects, tasks, or issues.

When you use this field in a report, a list of subscribers displays, with each subscriber separated by a comma.

For more information, see the article Subscribe to items in Adobe Workfront.

Summary TaskSee "Parent Task" in this article.
SubtaskA child task, which is located under a parent task.
System GovernanceA set of policies that governs changes and maintenance of a system.
System IntegrationThe process of linking together different computing systems and software applications physically or functionally in order to act as a coordinated whole.
Task

An activity that must be performed as a step toward achieving a final goal (completing the Project).

For more information, see Tasks overview.

Task AttributeOther fields or objects that are associated with a task and indicate certain details about the task. Some examples are Planned Completion Date and Status.
Task ConstraintSee "Constraint Type" and "Constraint Date".
Task ManagementA set of policies that governs the thresholds for task creation, assignment, closure, and visibility.
Task OwnerThe team or user responsible for the estimation of effort and completion of the task
Team

A collection of users working toward similar goals or business objectives. These users can be collectively assigned to a work item by assigning the team to the work item.

For more information on Teams, see Teams overview.

Projects can have a Project Team, which contains all the users or roles associated with the work on the project.

For more information about Project Teams, see Project Team overview

Template

Project templates are generic outlines of your most repeatable projects. You can define tasks, queue topics, custom forms, attach documents or approvals when you create a project template to save you time when you must create a new project.

You can attach templates to existing projects, or you can use them to build new projects. All the information specified on the template transfers to the projects that are created using it.

For more information about templates, see Project template overview.

Template TaskA task that is part of a template. Template Tasks become Tasks in the project that is created by using the template.
ThreadA Note and its collection of replies that relate to a particular topic.
Thumbnail

In a Document list or report, it displays a preview of the document in a thumbnail.

Select Thumbnail  to view a 33-66 pixel-wide thumbnail in the report.

The size of the thumbnail adjusts when you modify the width of the column in a list or report.

See also "Large Thumbnail" in this article.

Time OffYou can build a Time Off report to view when users have indicated time off in their profile.
TimesheetA timecard that allows users to enter actual hours that they spent working on projects, tasks, or issues, or hours they spent for other activities not related to work, like meetings or training. In addition to entering the amount of time you spent working, you can also indicate whether the time is work-related or it amounts to overhead time by using Hour Types to define your time entries. For information about timesheets, see Timesheets overview.
Timesheet Profile

A Timesheet Profile is a template that Workfront uses to automatically create timesheets for the users associated with them.

You can configure a number of settings that will apply to each timesheet as it is created. Some of these settings are: how often the timesheet should be created (weekly, every other week, twice a month, or monthly), the start day of the timesheet, the timesheet approvers, the available Hour Types that users can associate with recorded hours.

Top Parent IDThis field allows you to identify and filter data about a top-level group and its subgroups in a list or report.
Top Parent Name

This field allows you to identify data about a top-level group and its subgroups in a View for a list or report.

You can also do this using the Top Parent ID field.

Total Hours

In a project report, this field displays the rounded sum of all hours on the project, the last time the project finances were calculated. Actual Hours reflect the exact hours logged on the project. Typically, the Actual Hours should match the Total Hours. If the Total Hours appears significantly different from the Actual Hours field, you must Recalculate Finances on the project.

For more information about recalculating project finances, see the article Recalculate project finances.

In a timesheet Standard view, this field refers to the total hours logged for items for the dates displayed on a timesheet. The Total Hours field for timesheets in this built-in view references the "hoursDuration" field which dynamically calculates the difference in hours between the timesheet Start and End dates. This is used to display the Total Hours column in red if the user logs more time than the available hours in the timesheet's time frame. For more information, see View total hours on the timesheet.

Tracking Mode

An attribute of a task. This determines how and when the Projected timelines will be updated for a task. For example:

  • User Must Update requires that a task be updated manually. Otherwise, it will become Behind Schedule, then Late.
  • Auto Complete will automatically complete a task when the Due Date, or Planned Completion Date, has passed.

For more information, see Task Tracking Mode overview.

TriggerAn event that starts a scenario.
Trouble TaskAn incomplete task with a condition of Late, Behind Schedule, or At Risk.
Unassigned TaskA task that is not assigned to any User, Role, or Team.
Update Type

A setting on a project that determines when the project's Projected timeline will be recalculated. The Update Type can have the following values:

  • Automatic and On Change
  • Automatic Only
  • Manual Only

For more information, see Select the project Update Type.

UserAn account created in Workfront to allow a person to log in and interact with the system.
User Delegation

A reportable object that tells you:

  • Which users have delegated task, issue, and project approvals
  • Which users have had task, issue, and project approvals delegated to them
  • When these delegations start and end

To learn more, see Create a User Delegation report.

User InterfaceAll visual and interactive aspects of the Workfront application.
User Interface PreferencesUser Interface Setup. Workfront administrators can change these settings to customize aspects of the user interface.
UtilizationThe availability for a user or role based on the assigned schedule, PTO, and current workload.
User UtilizationA search combined with a report that shows how Users (Resources) are allocated or over-allocated. See "Resource Utilization" in this article.

V - Z

Object NameDescription
VelocityA measure of the total work cycle time (how long it takes to complete a piece of work) and how frequently work is done in the time originally committed (work-to-commit ratio).
View

Views refer to a reporting element which allows you to modify the columns in a report or in a list of objects.

View also refers to a user's right to only view information on an object, according to their access level or at a permissions sharing level on that object.

In Workfront Planning, records display on the record type page in one of the following view types:

  • Table
  • Timeline
  • Calendar

In Workfront Planning, views include the filters, groupings, sorting, and other settings applied to the records on the screen.

For information, see Manage record views.

Workfront Planning requires an additional license.

View Icons

This is the same field as Status Icons, but it is only available for the following views:

  • Documents

For more information, see the article Built-in Status Icons in Views.

Views Last MonthIn a report list, it displays the number of times the report has been viewed during the last month.
For more information about usage information in report lists, see the article View report usage.
Views Last QuarterIn a report list, it displays the number of times the report has been viewed during the last quarter.
For more information about usage information in report lists, see the article View report usage.
Views Last YearIn a report list, it displays the number of times the report has been viewed during the last year.
For more information about usage information in report lists, see the article View report usage.
Views This MonthIn a report list, it displays the number of times the report has been viewed during this month.
For more information about usage information in report lists, see the article View report usage.
Views This QuarterIn a report list, it displays the number of times the report has been viewed during this quarter.
For more information about usage information in report lists, see the article View report usage.
Views This YearIn a report list, it displays the number of times the report has been viewed during this year.
For more information about usage information in report lists, see the article View report usage.
widthIn a report, when using the Text Mode interface, the line of code where you can specify the width of each column in pixels. Workfront provides a suggested width for each field, though depending on the type of field and format, you may want to make adjustments. You must use the additional usewidths=true line of code to enforce the width specified for the column.
work

In a project, task, or issue report, using the following statement in text mode displays the Planned Hours of the project, task, or issue:

``

valuefield=work

valueformat=HTML

For information about using text mode, see Text mode syntax overview.

TIP

In an issue report, adding one of the Planned Hours fields adds the work field to the report.

Work

One of the two primary License Types. This has less access than Plan, but can create and make updates in the system. A user with a Work license has more abilities than an External, Reviewer, or Requester license holder.

For more information, see Adobe Workfront licenses overview.

Work might refer to the number of Planned Hours for a project, task, or issue. For more information, see the "work" field in this table.

TIP

In an issue report, adding one of the Planned Hours fields adds the work field to the report.

Work Breakdown StructureA hierarchical structure of the tasks to be executed by the project team based on the parent/ child relationship.
Work Effort

A project manager might decide to use this field instead of Planned Hours to estimate the effort needed to complete a task. This field is visible only when the following conditions are met:

  • The task has a Simple Duration Type.

    TIP

    If you update the task Duration Type to any other type, this field becomes hidden.

  • The project manager has enabled the Use Work Effort to automatically calculate task Planned Hours field on the project.

For information about using Work Effort instead of Planned Hours to estimate task effort, see Work Effort overview.

You can display this field in task reports and lists.

Work Item

This field refers to either tasks or issues in Workfront.

The Work Item report displays information for both tasks and issues.

Work management mixA Work Performance Indicator (WPI) of the proportion of work allocated to run your business versus change your business. The Mix WPI helps you understand, at an organizational level, whether your strategy has any real work allocation applied to it.
Work Management ResourceA designation of a persona in the system who is eligible to receive work or track time.
Work Management Role and ResponsibilitiesDefining the owners and stakeholders for managing the scope, execution, and approvals of the designated issue, task, project, program, or portfolio.
Work management SLAA quantifiable metric agreed upon by all stakeholders.
Work Management StakeholderA collection of users with a vested interest in the outcomes of a work request.
Work management touchpointsDigitized records of communication between stakeholders.
Work Performance Indicators

Mix ratio, capacity, velocity, quality, and engagement.

WPI is a common acronym for Work Performance Indicator.

Work Process

The method in which work is received, prioritized, and executed. The way you execute the work is typically called "the workflow" or "project plan" (a list of tasks with dates, predecessor relationships, and so forth).

Examples of a work process might be the production of a single asset or the delivery of a multi-asset campaign.

Workflow templateIn the Proof Approval report, this field displays any workflow templates attached to a proof. If there are no templates attached, the column is blank.
Work Time

Represents the percentage of the Full Time Equivalent (FTE) time that the user is available for actual work, not including overhead. Work Time must be a decimal number up to 1, and it cannot be 0. For example, a 20% availability for actual work would be 0.2.

The field's default is 1, indicating that a user spends their entire FTE on actual, project-related work.

The system uses this number to calculate the availability of the user for actual, project-related work.

Schedule exceptions and time off might also affect the user capacity.

For more information about creating schedules in Workfront, see Create a schedule.

Workfront calculates a user's availability depending on the Resource Management preferences in the Setup area. For more information, see Configure Resource Management preferences.

You can update the Work Time of a user when you edit or create the user. For information, see Edit a user's profile

TIP

Set the Work Time value to 1 to indicate that the user is available for project-related work their entire full-time equivalent.

Working timeIn Workfront documentation, this term is used to describe the time allocated to work, according to a schedule.
workRequiredExpression

In a project, task, or issue report, using the following statement in text mode displays the number of Planned Hours of the project, task, or issue followed by the word "Hours":

``

valuefield=workRequiredExpression

valueformat=HTML

For information about using text mode, see Text mode syntax overview.

Workspace

In Workfront Planning, a workspace is a collection of record types that define the operational lifecycle of a certain organization. A workspace is the work frame of an organizational unit.

Workfront Planning requires an additional license.

For information, see Create workspaces.

Previous pageAdobe Workfront basics: article index
Next pageAdobe Workfront browser requirements

Workfront