Access requirements

Expand to view access requirements for the functionality in this article.

You must have the following access to perform the steps in this article:

Adobe Workfront planAny
Adobe Workfront license*

Current: Plan

Or

New: Standard

Access level configurationEdit access to Projects and Tasks
Object permissionsManage permissions to a project and its tasks

*To find out what plan, license type, or access you have, contact your Workfront administrator. For more information, see Access requirements in Workfront documentation.

Considerations for using Work Effort

  • When the project tasks have 0 Planned Hours and you enable the Use Work Effort to automatically calculate task Planned Hours setting on the project, the default level of Work Effort associated with them will be Medium. The Planned Hours automatically update for Simple Duration Type tasks. For more information, see the section Levels of Work Effort in this article.
  • When the project tasks have Planned Hours that are more than 0 and you enable the Use Work Effort to automatically calculate task Planned Hours setting on the project, the level of Work Effort updates according to the amount of Planned Hours without changing the amount of the Planned Hours for Simple Duration Type tasks. For more information, see the section How Workfront calculates Work Effort based on Planned Hours in this article.
  • When the project tasks have 0 Planned Hours and you enable the Use Work Effort to automatically calculate task Planned Hours setting on the project, then update the level of Work Effort from Medium to Small or Large, the Planned Hours also update. For more information, see the section How Workfront calculates Planned Hours based on Work Effort in this article.
  • When you inline edit tasks and modify both the Planned Hours and Work Effort field for task at the same time, the Planned Hours will be updated with the value you specify, whereas the Work Effort value is calculated based on your updated Planned Hours.
  • When you update the Work Effort value of a task, the Duration no longer auto-calculates based on the Planned Hours. For more information about how Duration calculates for Simple Duration tasks, see Duration Type overview: Simple.
  • When you change the Duration Type of a task from Simple to any other type, the Work Effort field is hidden on the task. The Planned Hours remain unchanged.
  • You cannot update the Work Effort level on a parent task. The Work Effort level for a parent task is automatically calculated based on the number of Planned Hours for the tasks which is a rollup of all the children tasks. For information about parent tasks, see Create subtasks.

Enable using Work Effort instead of Planned Hours

  1. Go to a project and click the More menu , then click Edit.

  2. Click Task Settings, then select the option Use Work Effort to automatically calculate task Planned hours. This is deselected by default.

    For more information about enabling the use of Work Effort on a project, see the “Tasks Settings” section in the Edit projects article.

  3. Click Tasks on the left panel , then click the name of a task to access it.

  4. Click the More menu , then click Edit. Ensure the task has a Simple Duration Type.

    TIP
    You can update the Work Effort for a task in the Task Details section as well.
  5. In the Overview area, click the Work Effort drop-down menu to correct the amount of effort needed to complete the task.

    For more information about updating the Work Effort field on a task, see the following articles:

Levels of Work Effort

As a project manager, you can identify three levels of Work Effort for your projects. Each level of effort equates with a percentage of daily time that users need to complete the task.

When setting up the level of Work Effort you have to ask yourself the question: “How much time should a user assigned to this task spend on it daily to get it done in time?”

The following table illustrates the possible levels of Work Effort and their default corresponding percentages. As a project manager, you can update the percentages to suit the needs of your organization. You do this as you edit a project. For information about editing projects, see Edit projects.

As a Workfront administrator, you define the Typical hours per work day in the Project Preferences area of Setup. This is the daily amount of time considered as working time. For information about configuring Project Preferences for your instance of Workfront, see Configure system-wide project preferences.

NOTE
In the examples below, we assume that the Workfront administrator has set the Typical hours per work day amount to 8 hours.
Level of Work EffortPercentage values
SmallA Small level of effort for completing a task is set to 25% of the Typical hours per work day. This means that a task assigned this level of Work Effort should take up to 2 hours a day to complete in one day. (0.25*8=2)
Medium

A Medium level of effort for completing a task is set to 50% of the Typical hours per work day. This means that a task assigned this level of Work Effort should take more than 2 and less than 6 hours to complete in one day. (0.50*80=4)

Note: When the Use Work Effort to automatically calculate task Planned Hours setting is enabled on the project this is the default setting for a task, if the task had 0 Planned Hours before this setting was enabled. This causes the task Planned Hours to update to 4 hours.

LargeA Large level of effort for completing a task is set to 75% of the Typical hours per work day. This means that a task assigned this level of Work Effort should take 6 hours or more to complete in one day. (0.75*8=6)

How Workfront calculates Planned Hours based on Work Effort

When you enable the Use Work Effort to automatically calculate task Planned Hours setting on a project, Workfront calculates the number of Planned Hours for a task with a Simple Duration Type using the following formula:

Task Planned Hours = Number of days in task Duration * Work Effort percentage * Typical hours per work day

For example, a task with a Duration of 3 days and a Work Effort of Medium has 12 Planned Hours:

Planned Hours = 3*4=12

where the Typical hours per work day value is 8 hours.

TIP
When a task is assigned to multiple resources, the Planned Hours are evenly distributed to each resource for each day of the task’s duration.

How Workfront calculates Work Effort based on Planned Hours

When you enable the Use Work Effort to automatically calculate task Planned Hours setting on a project and you already have Planned Hours on the task or you edit the number of Planned Hours on the task, Workfront updates the Work Effort value.

Workfront uses the following formula to update the level of Work Effort according to the Planned Hours:

Work Effort level = Task Planned Hours / Duration / Typical hours per work day

For example, if you have a task with a Duration of 2 days and you update the Planned Hours from 8 to 20 hours, the Work Effort for the task updates from Medium to Large:

Work Effort level = 20 / 2 / 8 = 125 % = Large

Locate Work Effort for tasks and projects

Work Effort for projects

You can locate the Work Effort section on a project in the following area:

  • The Task Settings area in the Edit Project box

Work Effort for tasks

You can locate the Work Effort field for a task in the following areas:

  • The Overview area in the Edit Task box
  • The Overview area of the Task Details section, in the Working time area
  • A task list or report
Previous pagePlanned Hours overview
Next pageTask Progress Status overview

Workfront


Learn: Automating Workflows with Workfront Fusion - Unique Use Cases in Action

Workfront

Tuesday, Mar 4, 6:00 PM UTC

Looking for creative ways to use Workfront Fusion to solve business challenges? Join Pan Shahbazian of Starbucks as she shares three unique use cases that can transform your workflows.

Register

The Perfect Blend: A New Era of Collaboration with AEM and Workfront

Adobe Customer Success Webinars

Wednesday, Apr 2, 5:00 PM UTC

Explore how Adobe Experience Manager and Workfront integrate to help teams move from ideation to delivery without the usual bottlenecks, ensuring content is organized, on-brand, and ready to go live faster.

Register

Connect with Experience League at Summit!

Get front-row access to top sessions, hands-on activities, and networking—wherever you are!

Learn more

Register to learn something new

WORKFRONT

Join Adobe product experts in live events where you will learn Adobe Workfront best practices, tips and tricks, and hear about the latest product features and updates.

Register