How Workfront updates Project Condition based on Progress Status
When the Condition Type of the project is set to Manual, you can determine what the Condition of the project is independently from the Progress Status of the project.
However, we recommend that you set the Condition Type of the project to Progress Status so that you can have a clear indication of what the true progress of the project is, based on the progress of your tasks. For information about how Workfront calculates the Progress Status of projects, see Project Progress Status overview.
In this case, the values for the Project Condition can be:
Conditions can be customized for your environment, so you may find more than three options for Condition in your environment. The names of the Conditions might be different than the ones listed above. For information about customizing Conditions in , see the article Create or edit a custom condition.