Complicated example: project has children tasks
PIM = Hour-Based
EAC Method = Calculate at project level
-
Create Project A with six tasks where Task 3 is the parent of Tasks 4 and 5 and Task 1 is the parent of Tasks 2 and 3 as shown below:
Task 1
Task 2
Task 3
Task 4
Task 5
Task 6 -
Assign Tasks 2, 4, 5, and 6 to User 1 whose cost/hr rate is $100.00.
-
Add planned/ actual hours each task and % Complete according to the table below.
NOTE
For Tasks 1 and 3, you are only adding actual hours.
Task | Pln Hrs | Act Hrs | % Complete |
---|---|---|---|
Task 1 | 10 hrs | ||
Task 2 | 5 hrs | 10 hrs | 20% |
Task 3 | 10 Hrs | ||
Task 4 | 10 hrs | 10 hrs | 40% |
Task 5 | 15 hrs | 10 hrs | 50% |
Task 6 | 20 hrs | 10 hrs | 60% |
-
Add 50 hours directly to the project (More>Hours>Log Hours).
-
CPI for Task 2 = .1 calculated as follows:
CPI for Task 2 = IF Actual Hours > 0 THEN CPI = TotalBudgetedCostWorkPerformed/Actual Hours
ELSE CPI = 1
CPI for Task 2 = 1 / 10
CPI for Task 2 = .1 -
EAC for Task 2 = 50 hrs calculated as follows:
EAC for Task 2 = IF CPI <> 0 THEN EAC = Planned Hours/CPI
ELSE EAC = Planned Hours + Actual Hours
EAC for Task 2 = 5 / .1
EAC for Task 2 = 50 hrs -
The CPI / EAC for Tasks 4, 5, and 6 are as follows:
Task 4: .4 / 25 hrs
Task 5: .75 / 20 hrs
Task 6: 1.2 / 16.67 hrs -
CPI for Task 3 = .38 calculated as follows:
CPI for Task 3 = IF Actual Hours > 0 THEN CPI = TotalBudgetedCostWorkPerformed/Actual Hours
ELSE CPI = 1
CPI for Task 3 = 11.5 / 30
CPI for Task 3 = .38 -
EAC for Task 3 = 65.22 hrs calculated as follows:
EAC for Task 3 = IF CPI <> 0 THEN EAC = Planned Hours/CPI
ELSE EAC = Planned Hours + Actual Hours
EAC for Task 3 = 25 / .383333
EAC for Task 3 = 65.22 hrs -
CPI for Task 1 = .25 calculated as follows:
CPI for Task 1 = IF Actual Hours > 0 THEN CPI = TotalBudgetedCostWorkPerformed/Actual Hours
ELSE CPI = 1
CPI for Task 1 = 12.5 / 50
CPI for Task 1 = .25 -
EAC for Task 1 = 120 hrs calculated as follows:
EAC for Task 1 = IF CPI <> 0 THEN EAC = Planned Hours / CPI
ELSE EAC = Planned Hours + Actual Hours
EAC for Task 1 = 30/ .25
EAC for Task 1 = 120 hrs -
CPI for Project = .22 calculated as follows:
CPI for Project = IF Actual Hours > 0 THEN CPI = TotalBudgetedCostWorkPerformed/Actual Hours
ELSE CPI = 1
CPI for Project = 24.5 / 110
CPI for Project = .22272
CPI for Project = .22 -
EAC for Project = 224.49 hrs calculated as follows:
EAC for Project = IF CPI <> 0 THEN EAC = Planned Hours/CPI
ELSE EAC = Planned Hours + Actual Hours
EAC for Project = 50 / .22272
EAC for Project = 224.49 hrs
PIM= Cost-Based
Simple example: project has no children tasks
PIM = Cost-Based
EAC Method = Calculate at project level
- Create Project A with three tasks (no child tasks) all assigned to User 1 whose cost/hr is $100.00.
- Add planned/ actual hours to each task and % Complete according to the table below:
Task | Pln Hrs | Pln Lbr Cost | Act Hrs | Act Lbr Cost | % Complete |
---|---|---|---|---|---|
Task 1 | 5 hrs | $500.00 | 25 hrs | $2,500.00 | 20% |
Task 2 | 10 hrs | $1,000.00 | 25 hrs | $2,500.00 | 30% |
Task 3 | 15 hrs | $1,500.00 | 25 hrs | $2,500.00 | 40% |
- Add expenses to each task according to the table below:
Task | Expense | Planned Amount | Actual Amount |
---|---|---|---|
Task 1 | Task 1 Exp 1 | $300.00 | $400.00 |
Task 1 | Task 1 Exp 2 | $500.00 | $0.00 |
Task 2 | Task 2 Exp | $200.00 | $100.00 |
Task 3 | Task 3 Exp | $800.00 | $700.00 |
- Add two expenses to the project (i.e. not tied to a task) as follows:
Expense | Planned Amount | Actual Amount |
---|---|---|
Project Exp 1 | $1,000.00 | $1,500.00 |
Task 1 Exp 2 | $2,500.00 | $0.00 |
- Based on the above values, the Incurred/ Not Incurred Costs are determined as follows:
Task | Not Incurred Planned Expense | Incurred Planned Expense | Incurred Actual Expense |
---|---|---|---|
Task 1 | $500.00 | $300.00 | $400.00 |
Task 2 | $0.00 | $200.00 | $100.00 |
Task 3 | $0.00 | $800.00 | $700.00 |
Project | $3,000.00 | $2,300.00 | $2,700.00 |
-
From Project Actions, run Recalculate Finance
-
CPI for Task 1 = .14
-
CPI****for Task 1 = .14 calculated as follows:
CPI for Task 1 = IF Actual Labor Cost + IncurredActualExpenseCost <> 0 THENCPI = (TotalBudgetedCostWorkPerformed + IncurredPlannedExpenseCost) / (ActualLaborCost + IncurredActualExpenseCost)
ELSE CPI = CPI_Labor
CPI****for Task 1 = (100+300) / (2500+400)
CPI for Task 1 = 400 / 2900
CPI for Task 1 = .14**** -
EAC****for Task 1 = $13,400.00
CPI Labor for Task 1 = IF Actual Labor Cost <> 0 THENCPI_Labor = TotalBudgetedCostWorkPerformed/Actual Labor Cost
ELSE CPI_Labor = 1
CPI Labor for Task 1 = 100/2500
CPI Labor for Task 1 = .04 EAC Labor for Task 1 = IF CPI_Labor <> 0 THEN EAC Labor = Planned Labor Cost/CPI_Labor
ELSE EAC Labor = Planned Labor Cost + Actual Labor Cost
EAC Labor****for Task 1 = 500.00/.04
EAC Labor****for Task 1 = $12,500.00
EAC Expense****for Task 1 = IncurredActualExpenseCost + NotIncurredPlannedExpense
EAC Expense****for Task 1 = $400.00 + $500.00
EAC Expense****for Task 1 = $900.00
EAC****for Task 1 = EAC Labor + EAC Expense
EAC****for Task 1 = $12,500.00 + $900.00
EAC****for Task 1 = $13,400.00 -
Here are the CPI / EAC values for Task 2 and Task 3:
Task 2 = .19 / $8,433.33
Task 3 = .44 / $6,950.00 -
CPI for Project = .32 calculated as follows:
CPI****for Project = IF Actual Labor Cost + IncurredActualExpenseCost <> 0 THENCPI = (TotalBudgetedCostWorkPerformed + IncurredPlannedExpenseCost)/ActualLaborCost + IncurredActualExpenseCost)
ELSE CPI = CPI_Labor
CPI****for Project = (1000 + 2300) / (7500 + 2700)
CPI****for Project = 3300 / 10200
CPI****for Project = .32 -
EAC for Project = $28,200.00 calculated as follows:
CPI Labor****for Project = IF Actual Labor Cost <> 0 THENCPI_Labor = TotalBudgetedCostWorkPerformed/Actual Labor Cost
ELSE CPI_Labor = 1
CPI Labor****for Project = 1000 / 7500
CPI Labor****for Project = .13333
CPI Labor****for Project = .13EAC Labor****for Project = IF CPI_Labor <> 0 THEN
EAC Labor = Planned Labor Cost/CPI_Labor
ELSE EAC Labor = Planned Labor Cost + Actual Labor Cost
EAC Labor****for Project = 3000/ .13333
EAC Labor****for Project = $22,500.00EAC Expense****Project =
IncurredActualExpenseCost + NotIncurredPlannedExpense
EAC Expense****Project = $3000.00 + 2,700.00
EAC Expense****Project = $5,700.00EAC****Project = EAC Labor + EAC Expense
EAC****Project = $22,500.00 + $5,700.00
EAC****Project = $28,200.00
Complicated example: project has children tasks
PIM = Cost-Based
EAC Method = Calculate at project level
-
Create Project A with six tasks where Task 3 is the parent of Tasks 4 and 5 and Task 1 is the parent of Tasks 2 and 3 as shown below:
Task 1
Task 2
Task 3
Task 4
Task 5
Task 6 -
Assign Tasks 2, 4, 5, and 6 to User 1 whose cost/hr rate is $100.00.
-
Add planned/actual hours each task and % Complete according to the table below.
NOTE
For Tasks 1 and 3, you are only adding actual hours.
Task | Pln Hrs | Pln Lbr Cost | Act Hrs | Act Lbr Cost | % Complete |
---|---|---|---|---|---|
Task 1 | 10 hrs | $1,000.00 | |||
Task 2 | 5 hrs | $500.00 | 10 hrs | $1,000.00 | 20% |
Task 3 | 10 Hrs | $1,000.00 | |||
Task 4 | 10 hrs | $1,000.00 | 10 hrs | $1,000.00 | 40% |
Task 5 | 15 hrs | $1,500.00 | 10 hrs | $1,000.00 | 50% |
Task 6 | 20 hrs | $2,000.00 | 10 hrs | $1,000.00 | 60% |
- Add 50 hours directly to the project (More>Hours>Log Hours) so that there is $5,000.00 of actual labor cost recorded directly to the project. ****
- Add expenses to each task according to the table below (I’ve added a blank row in between each task to make it easier to read):
Task | Expense | Planned Amount | Actual Amount |
---|---|---|---|
Task 1 | Task 1 Exp 1 | $300.00 | -$400.00 |
Task 1 | Task 1 Exp 2 | -$500.00 | $800.00 |
Task 1 | Task 1 Exp 3 | $400.00 | $0.00 |
Task 2 | Task 2 Exp 1 | $500.00 | $700.00 |
Task 2 | Task 2 Exp 2 | -$400.00 | $0.00 |
Task 2 | Task 2 Exp 3 | -$200.00 | $600.00 |
Task 2 | Task 2 Exp 4 | $700.00 | -$200.00 |
Task 3 | Task 3 Exp | $0.00 | $1,000.00 |
Task 4 | Task 4 Exp 1 | $800.00 | $0.00 |
Task 4 | Task 4 Exp 2 | -$100.00 | $300.00 |
Task 4 | Task 4 Exp 3 | -200.00 | $0.00 |
Task 5 | Task 5 Exp 1 | $700.00 | $800.00 |
Task 5 | Task 5 Exp 2 | -$100.00 | $300.00 |
Task 5 | Task 5 Exp 3 | -$400.00 | -$200.00 |
Task 6 | Task 6 Exp 1 | $600.00 | $700.00 |
Task 6 | Task 6 Exp 2 | $500.00 | -$300.0 |
- Add two expenses to the project (i.e. not tied to a task) as follows:
Expense | Planned Amount | Actual Amount |
---|---|---|
Project Exp 1 | $1,000.00 | $1,500.00 |
Task 1 Exp 2 | $2,500.00 | $0.00 |
- Based on the above values, the Incurred/Not Incurred Costs are determined as follows:
Task | Not Incurred Planned Expense | Incurred Planned Expense | Incurred Actual Expense |
---|---|---|---|
Task 1 | $400.00 | -$500.00 | $800.00 |
Task 2 | -$400.00 | $300.00 | $1,300.00 |
Task 3 | $0.00 | $0.00 | $1,000.00 |
Task 4 | $600.00 | -$100.00 | $300.00 |
Task 5 | $0.00 | $600.00 | $1,100.00 |
Task 6 | $0.00 | $600.00 | $700.00 |
Project | $2,500.00 | $1000.00 | $1,500.00 |
-
From Project Actions, run Recalculate Finance
-
CPI for Task 2 = .17 calculated as follows:
CPI Task 2 = IF Actual Labor Cost + IncurredActualExpenseCost <> 0 THEN CPI = (TotalBudgetedCostWorkPerformed + IncurredPlannedExpenseCost) / (ActualLaborCost + IncurredActualExpenseCost)
ELSE CPI = CPI_Labor
CPI****Task 2 = (100+300) / (1000+1300)
CPI****Task 2 = 400 / 2300
CPI****Task 2 = .17 -
EAC for Task 2 = $5,900.00
CPI Labor****Task 2 = IF Actual Labor Cost <> 0 THEN CPI_Labor = TotalBudgetedCostWorkPerformed / Actual Labor Cost
ELSE CPI_Labor = 1
CPI Labor****Task 2 = 100/1000
CPI Labor****Task 2 = .1EAC Labor****Task 2 = IF CPI_Labor <> 0 THEN
EAC Labor = Planned Labor Cost/CPI_Labor
ELSE EAC Labor = Planned Labor Cost + Actual Labor Cost
EAC Labor****Task 2 = 500.00/.1
EAC Labor****Task 2 = $5,000.00 EAC Expense Task 2 = IncurredActualExpenseCost + NotIncurredPlannedExpense
EAC Expense****Task 2 = $1,300.00 + -$400.00
EAC Expense****Task 2 = $900.00EAC****Task 2 = EAC Labor + EAC Expense
EAC****Task 2 = $5,000.00 + $900.00
EAC****Task 2 = $5,900.00 -
The CPI/EAC for Tasks 4, 5, and 6 are determined the same way so I’ll just provide those values below:
Task 4: .23 / $3,400.00
Task 5: .64 / $3,100.00
Task 6: 1.06 / $2,366.67 -
CPI for Task 3 = .31 calculated as follows:
CPI****Task 3 = IF Actual Labor Cost + IncurredActualExpenseCost <> 0 THENCPI = (TotalBudgetedCostWorkPerformed + IncurredPlannedExpenseCost)/(ActualLaborCost + IncurredActualExpenseCost)
ELSE CPI = CPI_Labor
CPI****Task 3 = (1,150 + 500) / (3000 + 2400)
CPI****Task 3 = 1650 / 5400
CPI****Task 3 = .31 EAC for Task 3 = $9,521.74 calculated as follows:
**CPI Labor Task 3** = IF Actual Labor Cost <> 0 THENCPI_Labor = TotalBudgetedCostWorkPerformed / Actual Labor Cost
ELSE CPI_Labor = 1
CPI Labor****Task 3 = 1150/3000
CPI Labor****Task 3 = .383333
CPI Labor****Task 3 = .38EAC Labor****Task 3 = IF CPI_Labor <> 0 THEN
EAC Labor = Planned Labor Cost / CPI_Labor
ELSE EAC Labor = Planned Labor Cost + Actual Labor Cost
EAC Labor****Task 3 = $2,500.00 / .383333
EAC Labor****Task 3 = $6,521.74EAC Expense****Task 3 = IncurredActualExpenseCost + NotIncurredPlannedExpense
EAC Expense****Task 3 = $2,400.00 + $600.00
EAC Expense****Task 3 = $3,000.00EAC****Task 3 = EAC Labor + EAC Expense
EAC****Task 3 = $6,521.74 + $3,000.00
EAC****Task 3 = $9,521.74 -
CPI for Task 1 = .16 calculated as follows:
CPI****Task 1 = IF Actual Labor Cost + IncurredActualExpenseCost <> 0 THENCPI = (TotalBudgetedCostWorkPerformed + IncurredPlannedExpenseCost) / (ActualLaborCost + IncurredActualExpenseCost)
ELSE CPI = CPI_Labor
CPI****Task 1 = (1250 + 300) / (5000 + 4500)
CPI****Task 1 = 1550 / 9500=
CPI****Task 1 = .16 -
EAC for Task 1 is $17,100.00 calculated as follows:
CPI Labor****Task 1 = IF Actual Labor Cost <> 0 THENCPI_Labor = TotalBudgetedCostWorkPerformed / Actual Labor Cost
ELSE CPI_Labor = 1
CPI Labor****Task 1 = 1250 / 5000
CPI Labor****Task 1 = .25EAC Labor****Task 1 = IF CPI_Labor <> 0 THEN EAC Labor = Planned Labor Cost / CPI_Labor
ELSE EAC Labor = Planned Labor Cost + Actual Labor Cost
EAC Labor****Task 1 = $3,000.00 / .25
EAC Labor****Task 1 = $12,000.00EAC Expense****Task 1 = IncurredActualExpenseCost + NotIncurredPlannedExpense
EAC Expense****Task 1 = $4500 + 600
EAC Expense****Task 1 = $5,100.00EAC****Task 1 = EAC Labor + EAC Expense
EAC****Task 1 = $12,000.00 + 5,100.00
EAC****Task 1 = $17,100.00 -
CPI for Project is .25
CPI****for Project = IF Actual Labor Cost + IncurredActualExpenseCost <> 0 THENCPI = (TotalBudgetedCostWorkPerformed + IncurredPlannedExpenseCost)/(ActualLaborCost + IncurredActualExpenseCost)
ELSE CPI = CPI_Labor
CPI****for Project = (2450 + 1900) / (11000 + 6700)
CPI****for Project = 4350 / 17700
CPI****for Project = .25 -
EAC for Project = $32,248.98 calculated as follows:
CPI Labor****for Project = IF Actual Labor Cost <> 0 THENCPI_Labor = TotalBudgetedCostWorkPerformed / Actual Labor Cost
ELSE CPI_Labor = 1
CPI Labor****for Project = 2450 / 11000
CPI Labor****for Project = .22272
CPI Labor****for Project = .22EAC Labor****for Project = IF CPI_Labor <> 0 THEN
EAC Labor = Planned Labor Cost / CPI_Labor
ELSE EAC Labor = Planned Labor Cost + Actual Labor Cost
EAC Labor****for Project = $5,000.00 / .22272
EAC Labor****for Project = $22,448.97959
EAC Labor****for Project = $22,448.98EAC Expense****Project = IncurredActualExpenseCost + NotIncurredPlannedExpense
EAC Expense****Project = $3,100.00 + $6,700.00
EAC Expense****Project = $9,800.00EAC****Project = EAC Labor + EAC Expense
EAC****Project = $22,448.98 + 9,800.00
EAC****Project = $32,248.98
More help on this topic
Workfront
- Workfront documentation
- Product announcements
- Administration and setup
- Adobe Workfront basics
- Agile
- Documents
- Manage Work
- Teams and groups
- Reporting
- Manage resources
- Review and approve work
- Timesheets
- Adobe Workfront Scenario Planner
- Adobe Workfront Goals
- Adobe Workfront Planning
- Adobe Workfront Integrations
- Workfront Proof
- Adobe Workfront API
- ProofHQ API
Learn: Automating Workflows with Workfront Fusion - Unique Use Cases in Action
Workfront
Tuesday, Mar 4, 6:00 PM UTC
Looking for creative ways to use Workfront Fusion to solve business challenges? Join Pan Shahbazian of Starbucks as she shares three unique use cases that can transform your workflows.
RegisterThe Perfect Blend: A New Era of Collaboration with AEM and Workfront
Adobe Customer Success Webinars
Wednesday, Apr 2, 5:00 PM UTC
Explore how Adobe Experience Manager and Workfront integrate to help teams move from ideation to delivery without the usual bottlenecks, ensuring content is organized, on-brand, and ready to go live faster.
RegisterAdobe Workfront at Summit
Register for these user sessions:
- Driving Marketing Agility and Scale: Transforming your Content Supply Chain with AI (attend online)
- The Future of Adobe Workfront (attend online)
- A Proven Framework to Boost Campaign Creation Speed (attend online)
- How Workfront Is Bringing Enterprise-Ready AI to Work Management (attend online)
- Adobe’s Top 10 Generative AI Capabilities to Accelerate Your Content Supply Chain (attend online)
Connect with Experience League at Summit!
Get front-row access to top sessions, hands-on activities, and networking—wherever you are!
Learn moreRegister to learn something new
WORKFRONT
Join Adobe product experts in live events where you will learn Adobe Workfront best practices, tips and tricks, and hear about the latest product features and updates.
Register