Prerequisites
You must meet all the prerequisites required to work with the Resource Planner. For more information, see Resource Planner overview.
Availability and allocation of resources
The columns that display the availability and allocation of your resources change depending on which view you apply to the Resource Planner. For information about displaying the information in the Resource Planner by Project, Role, or User see Resource Planner navigation overview.
Consider the following when changing your view to the Resource Planner:
-
When you apply the View by Project or View by Role views, you can see the following columns:
- Available Hours, FTE, or Cost
- Planned Hours, FTE, or Cost
- Budgeted Hours, FTE, or Cost
- Hours, FTE, or Cost Variance
- Net Hours, FTE, or Cost
-
When you apply the View by User view, you can see the following columns:
- Available Hours or FTE
- Planned Hours or FTE
- Hour or FTE Difference
- Planned Hours Allocation Percentage

View information by Hour, FTE, or Cost
-
Go to the Resource Planner.
By default, information displays by Hours in the Resource Planner.
-
Expand the drop-down menu.
-
Select from the following options:
-
(Conditional) If you selected Customize, indicate options in the Customize displayed metrics box to set up your custom view.
-
In the View type column on the left, select one of the following views:
- Project
- Role
- User
-
In the Display selected items section, select the type of information you want to display in the columns of the selected view. The following table shows what options are available in each view:
Option User View Project View Role View Available ✔ ✔ ✔ Planned ✔ ✔ ✔ Budgeted ✔ ✔ Variance ✔ ✔ Net ✔ ✔ Actual ✔ Difference ✔ Percent ✔ -
Select Use Planned (PLN) values in NET calculations to use Planned instead of Budgeted information when calculating the Net values in the Project and Role views.
When selecting this option Workfront calculates the Net values using the following formula:
Net = Available - Planned
TIP
This option is applied only when you select at least one option to customize the view in the Display selected items section. -
Click Save.
The customized view that includes your selected columns displays.
The Resource Planner lists the customized view as Custom in the Hours drop-down menu.
NOTE
You can have only one customized view.