View Planned Hours vs. Actual Hours per assignment in a task View

  1. Go to a list of tasks.

  2. From the View drop-down menu, select New View.

  3. In the Column Preview area, eliminate all columns except for one.

  4. Click the header of the remaining column and click Switch to Text Mode > Edit Text Mode.

  5. Remove the text you find in the Edit Text Mode box, and replace it with the following code:

    column.0.descriptionkey=name
    column.0.isInlineEditable=false
    column.0.link.linkproperty.0.name=ID
    column.0.link.linkproperty.0.valuefield=ID
    column.0.link.linkproperty.0.valueformat=int
    column.0.link.lookup=link.view
    column.0.link.valuefield=objCode
    column.0.link.valueformat=val
    column.0.linkedname=direct
    column.0.listsort=string(name)
    column.0.namekey=name.abbr
    column.0.querysort=name
    column.0.section=0
    column.0.shortview=false
    column.0.stretch=0
    column.0.valuefield=name
    column.0.valueformat=HTML
    column.0.width=150
    column.1.descriptionkey=workrequired
    column.1.isInlineEditable=false
    column.1.linkedname=direct
    column.1.listsort=doubleAsDouble(workRequired)
    column.1.namekey=workrequired.abbr
    column.1.querysort=workRequired
    column.1.section=0
    column.1.shortview=false
    column.1.stretch=0
    column.1.valuefield=workFieldLong
    column.1.valueformat=compound
    column.1.viewalias=workrequired
    column.1.width=100
    column.2.listdelimiter=
    column.2.listmethod=nested(assignments).lists
    column.2.name=Wrk Assignment(s)
    column.2.stretch=0
    column.2.type=iterate
    column.2.valueexpression=CONCAT(right(CONCAT('~~~',{assignmentPercent}),3),'% (', {workRequired}/60 ,' Hours) - ',{assignedTo}.{name})
    column.2.valueformat=HTML
    column.2.width=300
    column.3.descriptionkey=actualworkrequired
    column.3.isInlineEditable=false
    column.3.linkedname=direct
    column.3.listsort=intAsInt(actualWorkRequired)
    column.3.namekey=actualworkrequired.abbr
    column.3.querysort=actualWork
    column.3.section=0
    column.3.shortview=false
    column.3.stretch=100
    column.3.valuefield=actualWorkFieldLong
    column.3.valueformat=compound
    column.3.viewalias=actualworkrequired
    column.3.width=100
    column.4.listdelimiter=
    column.4.listmethod=nested(hours).lists
    column.4.name=Actual Hours
    column.4.stretch=0
    column.4.type=iterate
    column.4.valueexpression=CONCAT('(', {hours} ,' Hours) - ',{owner}.{name})
    column.4.valueformat=HTML
    column.4.width=300
    
  6. Click Done > Save View.