Filter: display incomplete cross-project predecessors

This task filter returns incomplete cross-project predecessors.

Access requirements

Expand to view access requirements for the functionality in this article.
table 0-row-2 1-row-2 2-row-2 3-row-2 layout-auto html-authored no-header
Adobe Workfront package Any
Adobe Workfront license

Contributor or Request to modify a filter

Standard or Plan to modify a report

Access level configurations

Edit access to Reports, Dashboards, Calendars to modify a report

Edit access to Filters, Views, Groupings to modify a filter

Object permissions Manage permissions to a report

For more detail about the information in this table, see Access requirements in Workfront documentation.

Filter cross-project predecessors

To apply this filter:

  1. Go to a list of tasks or a task report.

  2. From the Filter drop-down menu, select New filter.

  3. (Conditional) Click Text mode if you accessed the filter from a list or Switch to Text Mode, if you accessed the filter from a report.

  4. In the new area, paste the following code:

    predecessorsMM:projectID=FIELD:projectID
    predecessorsMM:projectID_Mod=ne
    percentComplete=100
    percentComplete_Mod=ne
    
  5. (Conditional) Click Save Filter if you accessed the filter from a report, or Apply, then Save as new if you accessed the filter from a task list.

recommendation-more-help
5f00cc6b-2202-40d6-bcd0-3ee0c2316b43