Filter: display incomplete cross-project predecessors
This task filter returns incomplete cross-project predecessors.
Access requirements
You must have the following access to perform the steps in this article:
table 0-row-2 1-row-2 2-row-2 3-row-2 layout-auto html-authored no-header | |
---|---|
Adobe Workfront plan | Any |
Adobe Workfront license* |
New:
Current:
|
Access level configurations |
Edit access to Reports, Dashboards, Calendars to modify a report Edit access to Filters, Views, Groupings to modify a filter |
Object permissions | Manage permissions to a report |
*For information, see Access requirements in Workfront documentation.
Filter cross-project predecessors
To apply this filter:
-
Go to a list of tasks or a task report.
-
From the Filter drop-down menu, select New filter.
-
(Conditional) Click Text mode if you accessed the filter from a list or Switch to Text Mode, if you accessed the filter from a report.
-
In the new area, paste the following code:
predecessorsMM:projectID=FIELD:projectID predecessorsMM:projectID_Mod=ne percentComplete=100 percentComplete_Mod=ne
-
(Conditional) Click Save Filter if you accessed the filter from a report, or Apply, then Save as new if you accessed the filter from a task list.