Filter: display incomplete cross-project predecessors
This task filter returns incomplete cross-project predecessors.
Access requirements
You must have the following access to perform the steps in this article:
*To find out what plan, license type, or access you have, contact your Workfront administrator.
Filter cross-project predecessors
To apply this filter:
-
Go to a list of tasks.
-
From the Filter drop-down menu, select New Filter.
-
Click Switch to Text Mode.
-
In the Set Filter Rules for your Report area, paste the following code:
predecessorsMM:projectID=FIELD:projectID predecessorsMM:projectID_Mod=ne percentComplete=100 percentComplete_Mod=ne
-
Click Save Filter.
recommendation-more-help