Add a Leveling Delay to a task

  1. Go to a task for which you want to add a Leveling Delay.

  2. Click the More icon to the right of the task name, then click Edit.

  3. Click Settings.

  4. Specify the Leveling Delay, in hours, then choose a unit of time.
    This is the time that the resource will be delayed starting the task due to resource conflicts.

    Select from the following options for units of time:

    • Minutes
    • Hours. This is the default.
    • Days
    • Weeks
    • Months
    • Elapsed Minutes
    • Elapsed Hours
    • Elapsed Days
    • Elapsed Weeks
    • Elapsed Months
    TIP
    Elapsed time is a unit of time for a task’s Duration. It is the time between the Planned Start Date and the Planned Completion Date of a task that includes holidays, weekends, and time off. In other words, elapsed time is the passage of calendar days.
  5. Click Save.

Previous pageSet Tracking Mode for tasks
Next pageUpdate task Cost Type

Workfront