Edit story information
Understand what information can be viewed and edited understand-what-information-can-be-viewed-and-edited
When viewing a story tile on the Kanban board, the information in the following table is available. You can edit most information inline, directly from the story tile.
These numbers are used to calculate and display the Percent Complete for each story.
The Percent Complete for each story and issue.
The Percent Complete for the iteration is calculated based on the Percent Complete for each story.
When updating Percent Complete for a story or issue, you can choose any number between 0 and 100.
Access requirements
You must have the following access to perform the steps in this article:
table 0-row-2 1-row-2 layout-auto html-authored no-header | |
---|---|
Adobe Workfront plan | Any |
Adobe Workfront license |
New: Standard or Current: Work or higher |
For more detail about the information in this table, see Access requirements in Workfront documentation.
View and edit information on a story tile
-
Click the Main Menu icon in the upper-right corner of Adobe Workfront, or (if available), click the Main Menu icon in the upper-left corner, then click Teams.
-
(Optional) Click the Switch team icon , then either select a new Kanban team from the drop-down menu or search for a team in the search bar.
-
Go to the Kanban board.
-
Expand the story tile to view all fields associated with the story.
-
(Optional) To edit a field, click the field, then make any changes.
You must have Edit rights to the task or issue in order to edit the story tile.
For more information about each field and whether it can be edited, see Understand what information can be viewed and edited.