Grouping: Project Sponsor for a task list

This task grouping allows you to group tasks by the Project Sponsor.

Group by project sponsor

Access requirements

Expand to view access requirements for the functionality in this article.

You must have the following access to perform the steps in this article:

table 0-row-2 1-row-2 2-row-2 3-row-2 layout-auto html-authored no-header
Adobe Workfront plan Any
Adobe Workfront license*

New:

  • Contributor to modify a filter

  • Standard to modify a report

Current:

  • Request to modify a filter

  • Plan to modify a report

Access level configurations

Edit access to Reports, Dashboards, Calendars to modify a report

Edit access to Filters, Views, Groupings to modify a filter

Object permissions Manage permissions to a report

*For information, see Access requirements in Workfront documentation.

Group by Project Sponsor for a task list

To apply this grouping:

  1. Go to a list of tasks.

  2. From the Grouping drop-down menu, select New Grouping.

  3. Click Switch to Text Mode.

  4. Remove the text in the area that displays and replace it with the following code:

    code language-none
    group.0.name=Project Sponsor
    group.0.valuefield=project:sponsor:name
    group.0.valueformat=string
    
  5. Click Done.

  6. Update the grouping name, then click Save Grouping.

recommendation-more-help