Synchronize data in the burndown chart
The burndown chart is synchronized automatically with data in your project or iteration. If the burndown chart ever becomes out of sync with data in the project or iteration, you can manually synchronize it.
Access requirements
You must have the following access to perform the steps in this article:
table 0-row-2 1-row-2 layout-auto html-authored no-header | |
---|---|
Adobe Workfront plan | Any |
Adobe Workfront license |
New: Light or higher or Current: Review or higher |
For more detail about the information in this table, see Access requirements in Workfront documentation.
Manually synchronize the burndown chart with data in your iteration
-
Click the Main Menu icon in the upper-right corner of Adobe Workfront, or (if available), click the Main Menu icon in the upper-left corner, then click Teams.
-
(Optional) Click the Switch team icon , then either select a new Scrum team from the drop-down menu or search for a team in the search bar.
-
Go to the iteration where you want to manually synchronize the burndown chart.
-
Click the synchronize icon next to the iteration name.