Considerations about plans

Consider the following when creating plans:

  • You can build plans for a team, a whole department, or even your entire company. Plans are large planning units that outline the strategy of a company at a high level.
  • The shortest plan can have a duration of 1 year. The longest plan can have a duration of 5 years.
  • You cannot do actual work on a plan. You can roughly estimate whether you have the resources and the budget required to start planning work. For example, if your company wants to expand and acquire a new office in a new location, the steps required to accomplish that can be outlined first in a plan at the upper-management level.
  • You can create multiple scenarios of the same plan. When your original plan has too many conflicting initiatives, you will want to create several scenarios where you can edit initiatives or budgets and costs to see what is the ideal situation for accomplishing the plan. Initiatives can conflict with one another when they try to use the same resources during the same time frame. You can then compare scenarios to see what makes the most sense and which one your company should adopt, before they start adding the actual work to accomplish it. For information about creating scenarios, see the article Create and compare plan scenarios in the Scenario Planner.
  • You can add multiple initiatives to a plan to indicate how smaller planning units will contribute to the completion of the plan. For example, when you plan to expand into a specific market, you can have multiple initiatives at the department level that ultimately contribute to accomplishing the expansion at all levels of the organization. For information about creating initiatives, see the article Create and edit initiatives in the Scenario Planner.
  • When you create a plan you are the only person who can view it. You must the plan with other users and they can access it if they have at least View access to Scenario Planner in their access level.

Job role information for plans

You can review job role general information for plans that indicates the amount of job roles available for the plan, as well as the amount of job roles required for the initiatives to complete. You can view this information in the Job Roles box in the plan’s header.

Job role box on plan

You can view the following in the job role box:

InformationDescription
FTE/ Hours indicatorThe (FTE) or (Hours) indicator next to the “Job Role” title indicates whether the plan was set up to use FTEs or Hours when it was created. The plan, all the scenarios, and initiatives use this unit.
AvailableThe number of job role FTEs or hours that are available for the current scenario.
RequiredThe number of job role FTEs or hours that are required by all the initiatives in the current scenario so that they can be completed.

For information about accessing a plan and viewing detailed information about job roles, see Create and edit plans in the Scenario Planner.

Financial information for plans

You can review financial information about a plan, specifically its planned budget, how that budget is utilized and what the Net Value of the plan is. The Net Value of a plan is based on the Net Value of its initiatives. You can view this information in the Financial and Summary boxes in the plan’s header.

Budget and net value boxes

You can view the following in the Financial and Summary boxes on the plan:

BudgetThis is the monetary amount that your company decides that is available for executing the plan. Workfront distributes the budget evenly for each month within the duration of the plan. Budgets are typically set for a year, but it could also be set for a 3 or 5 year period. The currency in the parentheses to the left of the Financial box title indicates the currency of your system.
Costs

This is the total amount of costs that come from all initiatives on the plan. Workfront calculates the plan's Costs using the following formula:

Plan Costs = SUM(Initiative Costs)

For information about how Initiative Costs are calculated, see Create and edit initiatives in the Scenario Planner.

UTIL (Budget utilization percentage)

This is a calculated percentage between the costs associated with initiatives and the budget defined for the plan.

Workfront calculates the budget utilization percentage for a plan using the following formula:

Utilization percentage = (Plan Costs* 100))/ Plan Budget

Costs are calculated using the following formula:

Plan Costs = SUM(Initiatives People Costs, Initiatives Fixed Costs)

Tip: The Utilization percentage is rounded and has one decimal.

Net Value area in the Summary box

This is a calculation of all Net Values of all initiatives in the plan.

Workfront calculates the Net Value for the plan using the following formula:

Plan Net Value = SUM(Initiative Planned Benefit - People Costs)

Or

Plan Net Value = SUM(Initiative Net Value)

For information about the Initiatives Net Values, see the article Initiatives overview in the Scenario Planner.

For information about accessing a plan and viewing detailed financial information about it, see Create and edit plans in the Scenario Planner.

Previous pageInitiatives overview in the Scenario Planner
Next pageUpdate initiative priorities in the Scenario Planner

Workfront


Learn: Automating Workflows with Workfront Fusion - Unique Use Cases in Action

Workfront

Tuesday, Mar 4, 6:00 PM UTC

Looking for creative ways to use Workfront Fusion to solve business challenges? Join Pan Shahbazian of Starbucks as she shares three unique use cases that can transform your workflows.

Register

The Perfect Blend: A New Era of Collaboration with AEM and Workfront

Adobe Customer Success Webinars

Wednesday, Apr 2, 5:00 PM UTC

Explore how Adobe Experience Manager and Workfront integrate to help teams move from ideation to delivery without the usual bottlenecks, ensuring content is organized, on-brand, and ready to go live faster.

Register

Connect with Experience League at Summit!

Get front-row access to top sessions, hands-on activities, and networking—wherever you are!

Learn more


Register to learn something new

WORKFRONT

Join Adobe product experts in live events where you will learn Adobe Workfront best practices, tips and tricks, and hear about the latest product features and updates.

Register