View Resolvable Objects in a task or project report

  1. Go to a list of tasks or projects which have been converted from issues.

  2. From the View drop-down menu, click New View.

  3. In the Column Preview area, click Add Column.

  4. Click the header of the new column, then click Switch to Text Mode > Edit Text Mode.

  5. Remove the text you find in the Edit Text Mode box, and replace it with the following code:

    displayname=Resolvables
    listdelimiter=<br>
    listmethod=nested(resolvables).lists
    textmode=true
    type=iterate
    valuefield=name
    valueformat=HTML
    
  6. Click Done > Save View.
    A list of all Resolvable Objects displays in the new column. The names of the objects in the list cannot be linked directly to the objects.

Previous pageView: reporting elements used in reports
Next pageView: show parent tasks up to 4 levels deep

Workfront

Get inspired by fellow certified Workfront users

Discover how two Workfront pros grew their skills and advanced their careers through Adobe certification—and how you can too.Read their stories

Register to learn something new

WORKFRONT

Join Adobe product experts in live events where you will learn Adobe Workfront best practices, tips and tricks, and hear about the latest product features and updates.