Learn to sequence tasks
Last update: March 17, 2025
- Topics:
- Work Management
CREATED FOR:
- Beginner
- User
The video explains how to sequence tasks in Workfront using predecessors and durations to manage project timelines effectively.
The video demonstrates how to set predecessors for new tasks, ensuring sequential order and accurate start dates.
It emphasizes the importance of practicing with predecessors to understand their impact on project timelines and recommends using durations and predecessors for efficient project planning.
Transcript
Take a look at the task list in your project. For the project to be successful, much of that work needs to be done at a certain time and in a certain order. In Workfront, this order is established by task predecessors. At its most basic, a predecessor is a task that another task depends on. Predecessors indicate that specific work needs to be done before other work can start. Some projects require tasks to fall in a certain linear or sequential order, and some may not. Workfront can account for all project types. Predecessors work in conjunction with durations. As you’re planning your project, durations establish the time frame during which a specific work item needs to be done. For example, the four-day duration on this task sets the planned start and completion dates. When you change the duration, the completion date changes. But it’s the predecessor that tells this task that another task must be completed before this one can start. Take a look at the predecessor column. It has the number 2 in it. That means task number 2 must be completed before this task can begin. And you see this sequence reflected in the dates on each of the tasks. The first task, the predecessor task, is slated to start on this date and end on this date. The next task, the successor task, is slated to start right after the other task finishes. As you look through the rest of the project, you see the predecessors have already been set. These came from the template used to create the project. When you change the duration of the first task, that adjusts the completion date, which, in turn, adjusts the start date of the successor task. Because predecessors are set up throughout the project, the change cascades throughout the task list. Note, Workfront recommends using durations and predecessors to establish the project timeline. Clicking into the date fields to pick a specific date changes what’s called a task constraint. The task’s original constraint can be set in the template. In turn, this constrains how the task dates behave and overrides the cascade of date updates when you make duration or predecessor changes. Predecessors can be changed when needed, and you need to add them when you add tasks to the project. Take a look at these three tasks. These tasks need to happen in this order after task number 12 is finished. Take a look at the start dates. They’re identical. By default, when you create a new task, Workfront makes the start date the same as the start date of the project. Let’s walk through this. Task 12 must be completed before any of these can start, so we’ll set the date to 13. Did you see the dates change? Now set the predecessors on the remaining tasks by entering the number of the predecessor task. Click out to save or hit tab to move to the next field. If you’re entering a bunch of predecessors in a row, click return to move to the next predecessor field in the list. Now you can see these tasks have sequential dates establishing the order in which the work needs to be done. Plus, it’s established the exact dates for when the work should be done. Note, you can enter multiple predecessors on a task. Just keep an eye on how this affects your project timeline. Take time to fine tune your predecessor skills with a few practice projects, paying attention to how changes to durations and predecessors affect the project timeline. This will be time well spent. Understanding how predecessors work is key to understanding and successfully managing your project timeline.
Key takeaways
- Predecessors Define Task Order: Predecessors establish the sequence of tasks, ensuring certain tasks are completed before others can begin, which is crucial for project success.
- Durations Impact Timelines: Task durations set the time frame for work and adjust start and completion dates, creating a cascading effect on dependent tasks.
- Templates Simplify Setup: Predecessors and constraints can be pre-set in project templates, streamlining the process of managing task sequences.
- Manual Adjustments Affect Constraints: Manually setting specific dates overrides the cascading updates caused by changes to durations or predecessors.
- Practice Improves Skills: Practicing with predecessors and durations helps refine project management skills and ensures better control over timelines.
Recommended tutorials on this topic
NOTE
This video is part of a playlist Plan a project!
Previous pageUnderstand task durations
Next pageUnderstand planned hours
Workfront
- Workfront Tutorials
- Administration and Setup
- Organizational setup
- Manage deleted items
- Configure system defaults
- Layout templates
- What are layout templates?
- Find layout templates
- Customize terminology with layout templates
- Customize the Main Menu with layout templates
- Add and manage pins through a layout template
- Customize Home with layout templates
- Assign and manage access to layout templates
- Customize object areas with a layout template
- Customize project details with layout templates
- Customize project headers with layout templates
- Customize reporting lists with layout templates
- Email and In App Notifications
- Create and manage users
- Approval processes and milestone paths
- System performance and maintenance
- Project finances
- Custom Data
- Custom Forms
- Calculated expressions
- Get started with calculated fields and expressions
- Learn the data expression structure
- Understand Date & Time and Mathematical expressions
- Create ADDDAYS, ADDWEEKDAY, ADDMONTHS, ADDYEARS expressions
- Use the Calculation Editor
- Create DATEDIFF and WEEKDAYDIFF expressions
- Create a SUB, SUM, DIV, or PROD data expression
- Use the CONCAT expression in a calculated field
- Create LEFT/RIGHT expressions
- Use the ISBLANK and CONTAINS expressions
- Create an IF text expression
- Things to know about calculated field expressions
- Manage work
- Projects
- Understand basic project creation
- Navigate the project page
- Learn four ways to create a project
- Fill in the project details
- Get started planning a project
- Take a project live
- Get started managing a project
- Find projects
- Share a project
- Understand the project team
- Understand project communication
- View project information
- Track overall project progress
- Track work progress with project metrics
- Understand the Gantt view
- Understand the Board view
- Tasks
- Issues/requests
- Request queues
- Portfolios
- Approval processes and milestone paths
- Create and manage project templates
- Project timelines
- Close a project
- Project finances for users
- Intermediate projects
- Projects
- Reporting
- Basic reporting
- Understand reporting elements
- Understand reporting components
- Create a basic grouping
- Create a basic view
- Add basic conditional formatting to a view
- Create a basic filter
- Understand the new filter experience
- Create basic filter activities
- Create a simple report
- Create a task report
- Copy a report
- Create reports with charts
- Create a matrix report
- Create dashboards
- Send and share reports
- Understand report settings
- Intermediate reporting
- Create filters with user-based wildcards
- Create filters with date-based wildcards
- Create OR statements in filters
- Understand built-in project filters
- Understand built-in task filters
- Understand built-in issue filters
- Understand basic text mode for filters
- Understand basic text mode for views
- Understand basic text mode for groupings
- Create custom prompts
- Advanced reporting
- Calendar reports
- Basic reporting
- Manage resources
- Workfront Goals
- Workfront Planning
- Integrations
- Adobe Creative Cloud
- Adobe Experience Manager Assets Essentials
- G Suite
- Jira
- Microsoft Outlook
- Microsoft Teams
- Adobe Workfront for Microsoft Teams Overview
- Install Adobe Workfront for Microsoft Teams
- Access Adobe Workfront from Microsoft Teams
- Search for and share Adobe Workfront items in Microsoft Teams
- Create Adobe Workfront tasks from Microsoft Teams
- Submit Adobe Workfront requests from Microsoft Teams
- Manage Adobe Workfront notifications in Microsoft Teams
- Slack
- Fusion
- Welcome to Workfront Fusion
- Understand the basics
- Initial scenario design walkthrough
- Initial scenario design exercise
- Mapping panel and formula editor
- Mapping panel important notes
- Beyond basic mapping walkthrough
- Beyond basic mapping exercise
- Use filters
- Filters walkthrough
- Filters exercise
- Access previous versions walkthrough
- Access previous versions exercise
- Universal connectors and routing
- Universal connectors exercise overview
- Introduction to universal connectors walkthrough
- Introduction to universal connectors exercise
- Understand routers
- Routers walkthrough
- Routers exercise
- Common routing patterns
- Routing patterns walkthrough
- Routing patterns exercise
- Set-it and get-it
- Get/Set variables walkthrough
- Set/Get variables exercise
- Iteration and aggregation
- Execution history and scheduling
- Beyond basic modules
- Data structures and data stores
- Final functional bits and bobs
- Troubleshooting and error handling
- Workfront Fusion administration
- Design optimization and testing
- Workfront Proof
- Learn the benefits of proofing
- Understand the difference between a document and a proof
- Proofing viewers explained
- Administration and setup
- What is an automated workflow template
- Customize proof comment actions
- Customize proof decision options
- Understand email alerts and proof notifications
- Proof roles and email alerts
- Report on proofs
- Set default at risk proof settings
- Set up global proof settings
- Set default proof roles
- Set up proof account default settings
- Settings for proof users
- Upload proofs
- What is a proof version
- Who uploads the proof versions
- Convert a document to a proof
- View and compare proof versions
- Upload a proof version
- Manage proof versions
- Upload a proof of a video
- Upload a proof of a website
- Upload a proof with a basic workflow
- Upload a proof with an automated workflow
- Upload with a drag and drop
- Combine multiple files into a single proof
- Proof workflows
- Review and approve work
- Workfront DAM
- System setup
- Metadata and keywords
- Brand Connect customization
- Workfront DAM user: Contributor
- Understand Workfront DAM as a contributor
- Understand asset management as a contributor
- Understand finding assets as a contributor
- Understand lightboxes as a contributor
- Understand metadata and keyword best practices
- Work with assets as a contributor
- Send a file as a contributor
- Publish assets as a contributor
- Add a Workfront DAM link
- Brand Connect user
- Home
- Agile
- Best Practices
- Agile
- API Explorer
- Business case and portfolio optimizer
- Communication
- Custom forms
- Custom reports
- Dashboards
- Documents
- Filters, views, and groupings
- Job roles
- Layout templates
- Licenses and access levels
- Onboarding and adoption
- Organization units
- Portfolios and programs
- Preview sandbox
- Project, task, and issue preferences
- Project templates
- Proofing
- Request queue
- Resource Planner
- Resource pools
- Scenario Planner
- Schedules
- Statuses
- System performance and maintenance
- Text mode reporting
- Timeline planning and management
- Timesheets and logging time
- Utilization
- Workfront Goals
- Workload Balancer
- Workfront for executives
Get inspired by fellow certified Workfront users
Discover how two Workfront pros grew their skills and advanced their careers through Adobe certification—and how you can too.Read their stories