Track overall project progress
Last update: March 14, 2025
CREATED FOR:
- Beginner
- User
The video explains how to track overall project progress using various indicators in Workfront, including Percent Complete, Projected Dates, Condition and Progress Status, Open Issues, and the Condition Update column.
The video emphasizes the importance of regular updates by team members and proactive issue management to ensure accurate tracking and timely project completion.
Transcript
There are a few quick things that you can do to get a feel for the overall progress of a project. We’ll look at Percent Complete, Projected Dates, Condition and Progress Status, Open Issues, and the Condition Update column. All of these indicators work best when you have a well-planned project and your project team members are updating their assigned tasks on a regular basis. In the Project Header, you can see the Percent Complete of the project. This is calculated by the Percent Complete values of each of the project tasks, weighted by either the duration or the planned hours of each task. Now we’ll talk about dates. We’ll go to the Project Details screen. When you plan your project, you can give it a planned start date. Then Workfront calculates the planned completion date based mostly on your task durations and predecessors. It also calculates two more dates, the Projected Start Date and the Projected Completion Date. These are the dates Workfront is projecting that you will meet if everything keeps going on the present course. Right now, the planned and the projected completion dates are the same. But what if we change the planned start date to last week? Now the planned completion date is recalculated to come in a week earlier, but the projected completion date is still August 2nd. That’s because no one’s reported doing any work on the project the last week. So the project is in danger of finishing late unless we take some action. Notice that the condition is showing At Risk now, which means it’s running behind but it’s not late yet. And you can see that the projected date is only a week past our planned completion date, so we may still be able to catch up. But what if I change the planned start date to a few months ago? It now shows a condition of In Trouble, which means the project is late. The planned completion date is now in the past. Let’s talk a little more about the Project Condition field. The Summer Catalog project has been running for some time now. The Project Condition says it’s on target, but this field can be set manually, so how do we know if it’s really on target or if the project manager just forgot to change the condition? You can hover over the condition to find out. If you’re given the option to change the condition, that means it’s in manual mode. The mode setting can be changed in Project Details. If we change it to Progress Status, it will use the Calculated Progress Status field instead. If you hover over the Condition field now, you get a message saying this field is automatically calculated by the system. It means you’re in Progress Status mode. But even if the system we’re calculating the condition is on target, you may still be at risk. You need to keep an eye on Open Issues. This number tells you how many open issues there are in this project. Open issues could mean that there is more work to be done than was expected. Best practice is to review new issues right away. If you decide they need to be resolved in this project, you can convert them to a task and plan them into the timeline. Until new issues are understood, you won’t know if they present a risk to your project. Let’s look at a project list to see one of the best ways to know the overall progress of a project. Change the view to the real story. And take a look at the Condition Update column. This shows the current condition and the most recent project update comment made by the project owner. A popular practice is for the project manager to make a brief entry summarizing the project progress at the end of each week. The most recent post will appear in this column if you choose the real story view or create a custom view.
Key takeaways
- Percent Complete Calculation: The overall project progress is calculated based on the Percent Complete values of individual tasks, weighted by their duration or planned hours.
- Planned vs. Projected Dates: Workfront calculates planned and projected start/completion dates based on task durations and predecessors. Discrepancies between these dates indicate potential delays.
- Project Condition Status: The condition field (e.g., On Target, At Risk, In Trouble) reflects the project’s status and can be set manually or automatically using Progress Status mode.
- Open Issues Management: Open issues signal potential risks. Reviewing and converting them into tasks promptly is essential for maintaining project timelines.
- Condition Update Column: Weekly updates from the project manager in the Condition Update column provide a clear summary of progress and help track the latest developments.
Recommended tutorials on this topic
Previous pageView project information
Next pageTrack work progress with project metrics
Workfront
- Workfront Tutorials
- Administration and Setup
- Organizational setup
- Manage deleted items
- Configure system defaults
- Layout templates
- What are layout templates?
- Find layout templates
- Customize terminology with layout templates
- Customize the Main Menu with layout templates
- Add and manage pins through a layout template
- Customize Home with layout templates
- Assign and manage access to layout templates
- Customize object areas with a layout template
- Customize project details with layout templates
- Customize project headers with layout templates
- Customize reporting lists with layout templates
- Email and In App Notifications
- Create and manage users
- Approval processes and milestone paths
- System performance and maintenance
- Project finances
- Custom Data
- Custom Forms
- Calculated expressions
- Get started with calculated fields and expressions
- Learn the data expression structure
- Understand Date & Time and Mathematical expressions
- Create ADDDAYS, ADDWEEKDAY, ADDMONTHS, ADDYEARS expressions
- Use the Calculation Editor
- Create DATEDIFF and WEEKDAYDIFF expressions
- Create a SUB, SUM, DIV, or PROD data expression
- Use the CONCAT expression in a calculated field
- Create LEFT/RIGHT expressions
- Use the ISBLANK and CONTAINS expressions
- Create an IF text expression
- Things to know about calculated field expressions
- Manage work
- Projects
- Understand basic project creation
- Navigate the project page
- Learn four ways to create a project
- Fill in the project details
- Get started planning a project
- Take a project live
- Get started managing a project
- Find projects
- Share a project
- Understand the project team
- Understand project communication
- View project information
- Track overall project progress
- Track work progress with project metrics
- Understand the Gantt view
- Understand the Board view
- Tasks
- Issues/requests
- Request queues
- Portfolios
- Approval processes and milestone paths
- Create and manage project templates
- Project timelines
- Close a project
- Project finances for users
- Intermediate projects
- Projects
- Reporting
- Basic reporting
- Understand reporting elements
- Understand reporting components
- Create a basic grouping
- Create a basic view
- Add basic conditional formatting to a view
- Create a basic filter
- Understand the new filter experience
- Create basic filter activities
- Create a simple report
- Create a task report
- Copy a report
- Create reports with charts
- Create a matrix report
- Create dashboards
- Send and share reports
- Understand report settings
- Intermediate reporting
- Create filters with user-based wildcards
- Create filters with date-based wildcards
- Create OR statements in filters
- Understand built-in project filters
- Understand built-in task filters
- Understand built-in issue filters
- Understand basic text mode for filters
- Understand basic text mode for views
- Understand basic text mode for groupings
- Create custom prompts
- Advanced reporting
- Calendar reports
- Basic reporting
- Manage resources
- Workfront Goals
- Workfront Planning
- Integrations
- Adobe Creative Cloud
- Adobe Experience Manager Assets Essentials
- G Suite
- Jira
- Microsoft Outlook
- Microsoft Teams
- Adobe Workfront for Microsoft Teams Overview
- Install Adobe Workfront for Microsoft Teams
- Access Adobe Workfront from Microsoft Teams
- Search for and share Adobe Workfront items in Microsoft Teams
- Create Adobe Workfront tasks from Microsoft Teams
- Submit Adobe Workfront requests from Microsoft Teams
- Manage Adobe Workfront notifications in Microsoft Teams
- Slack
- Fusion
- Welcome to Workfront Fusion
- Understand the basics
- Initial scenario design walkthrough
- Initial scenario design exercise
- Mapping panel and formula editor
- Mapping panel important notes
- Beyond basic mapping walkthrough
- Beyond basic mapping exercise
- Use filters
- Filters walkthrough
- Filters exercise
- Access previous versions walkthrough
- Access previous versions exercise
- Universal connectors and routing
- Universal connectors exercise overview
- Introduction to universal connectors walkthrough
- Introduction to universal connectors exercise
- Understand routers
- Routers walkthrough
- Routers exercise
- Common routing patterns
- Routing patterns walkthrough
- Routing patterns exercise
- Set-it and get-it
- Get/Set variables walkthrough
- Set/Get variables exercise
- Iteration and aggregation
- Execution history and scheduling
- Beyond basic modules
- Data structures and data stores
- Final functional bits and bobs
- Troubleshooting and error handling
- Workfront Fusion administration
- Design optimization and testing
- Workfront Proof
- Learn the benefits of proofing
- Understand the difference between a document and a proof
- Proofing viewers explained
- Administration and setup
- What is an automated workflow template
- Customize proof comment actions
- Customize proof decision options
- Understand email alerts and proof notifications
- Proof roles and email alerts
- Report on proofs
- Set default at risk proof settings
- Set up global proof settings
- Set default proof roles
- Set up proof account default settings
- Settings for proof users
- Upload proofs
- What is a proof version
- Who uploads the proof versions
- Convert a document to a proof
- View and compare proof versions
- Upload a proof version
- Manage proof versions
- Upload a proof of a video
- Upload a proof of a website
- Upload a proof with a basic workflow
- Upload a proof with an automated workflow
- Upload with a drag and drop
- Combine multiple files into a single proof
- Proof workflows
- Review and approve work
- Workfront DAM
- System setup
- Metadata and keywords
- Brand Connect customization
- Workfront DAM user: Contributor
- Understand Workfront DAM as a contributor
- Understand asset management as a contributor
- Understand finding assets as a contributor
- Understand lightboxes as a contributor
- Understand metadata and keyword best practices
- Work with assets as a contributor
- Send a file as a contributor
- Publish assets as a contributor
- Add a Workfront DAM link
- Brand Connect user
- Home
- Agile
- Best Practices
- Agile
- API Explorer
- Business case and portfolio optimizer
- Communication
- Custom forms
- Custom reports
- Dashboards
- Documents
- Filters, views, and groupings
- Job roles
- Layout templates
- Licenses and access levels
- Onboarding and adoption
- Organization units
- Portfolios and programs
- Preview sandbox
- Project, task, and issue preferences
- Project templates
- Proofing
- Request queue
- Resource Planner
- Resource pools
- Scenario Planner
- Schedules
- Statuses
- System performance and maintenance
- Text mode reporting
- Timeline planning and management
- Timesheets and logging time
- Utilization
- Workfront Goals
- Workload Balancer
- Workfront for executives