Kanban story execution

Note that you are using a Work In Progress limit of five stories. Looking at your board, you see that as you move tasks into status columns, the number of tasks in each lane shows at the top right of each status column.

Kanban WIP limits

If you exceed the limit in a status column equating to New or In Progress, you will get an error message indicating that you’ve gone over the work in progress limit.

Exceed WIP limits

If your team decides that they can handle more or less items at a time, you (and other team members with editing rights) can change the Work in Progress number right from the storyboard by clicking on the WIP number and editing it to reflect your new decision.

Previous pageCreate a Kanban team
Next pageFind and create a basic board