If you are a group administrator and an Adobe Workfront administrator unlocks a project preference for all groups in the system, you can configure that preference for your group to affect all subsequent projects that your group creates.
If there are any groups above the group you manage, their administrators can also do this for your group. The same is true for Workfront administrators (for any group).
Typically, an unlocked preference remains unlocked indefinitely. If the Workfront administrator re-locks it, the system setting takes effect again and settings for the preference made by the group administrators are lost.
The preferences set for the group that is associated with a project take precedence over the preferences set for the Home Group of the user who creates the project.
Some group-level preferences affect project templates that you create for the group. For more information, see the section View, work with, and create templates for your group from the Groups area in the article Create and modify a group’s project templates.
After a Workfront administrator unlocks a preference at the system level, you can configure it and then lock it to ensure that everyone in your group and in its subgroups is using the same configuration. This is parallel to the ability that a Workfront administrator has to configure and lock a preference for everyone in the system. For more information, see Lock or unlock a project, task, or issue preference for subgroups.
Group-level configuration is also possible for task and issue preferences and for timesheet and hour preferences. For information, see Configure task and issue preferences for a group and Configure timesheet and hour preferences for a group.
For information about how a Workfront administrator unlocks a project preference, see Lock or unlock project preferences for all groups in the system.
You must have the following to perform the steps in this article:
Workfront plan* | Any |
Adobe Workfront license* | Plan You must be a group administrator of the group or a Workfront administrator. For more information, see Group administrators and Grant a user full administrative access. |
*If you need to find out what plan or license type you have, contact your Workfront administrator.
If you are a Workfront administrator, you can bypass steps 1-4 by going to Setup > Project Preferences > Projects, then searching for the group’s name in the box at the top of the page.
Click the Main Menu icon in the upper-right corner of Adobe Workfront, then click Setup
.
In the left panel, click Groups .
Click the name of the group whose project preferences you want to configure.
In the left panel, click Project Preferences.
On the page that appears, continue with one of the 4 sections listed below to configure preferences for Project Status, Timelines, Business Cases, and Life after Death.
If you hover over a preference and a tool tip displays to tell you that it is locked, you can ask your Workfront administrator to unlock it for all groups in the organization.
Configure any of the following preferences for newly created projects associated with the group:
Allow users to create projects without using a template | This preference allows users to create projects without using a template when creating a project from the following areas:
This preference is enabled by default at the system level. NOTE When a user belongs to multiple groups with different preferences, the user will be allowed to create a project without a template if at least one of their groups has this preference enabled. |
Set new project's status to | Determine the status of new projects. NOTE
|
Calculate Percent Complete based on | The percent complete of a project or parent task is based on the overall progress of the tasks. This information can be calculated based on either the Duration or the Planned Hours of the tasks on a project. If you select Duration, the Duration of each task in a project determines the overall percent complete for the project, and the Duration of each subtask determines the overall percent complete for its parent task. If you select Duration, make sure you specify the Typical hours per work day and Typical work days per week in the Timelines section. Workfront uses this information when calculating a task's percent complete based on Duration. If you select Planned Hours, ensure that all tasks on each project have the amount of Planned Hours defined, and that the amount is not zero. |
Automatically set the project's Condition based on the Progress Status | This preference allows users to set the Condition of a project manually (On Target, At Risk, In Trouble) or have Workfront set the Condition (Progress Status) automatically based on the project's progression on the timeline. For more information about the Condition of projects, see Overview of Project Condition and Condition Type. |
Create baselines automatically |
This preference automatically creates a baseline (snapshot) of task and project details when the status of the project changes to Current. For information about creating baselines, see Create project baselines. |
Performance Index Method |
The Performance Index Method (PIM) for the project controls the method Workfront uses to calculate Earned Value metrics such as Cost Performance Index (CPI) and Estimate At Completion (EAC). For more information, see Calculate Cost Performance Index (CPI)and Calculate Estimate At Completion (EAC)
|
Estimate at Completion |
Determine which data Workfront uses to calculate the Estimate at Completion (EAC) which represents the projected total cost of a project.
For more information on how the EAC calculates, see Calculate Estimate At Completion (EAC). |
Configure any of the following preferences for newly created projects associated with the group:
Schedule From | Determine whether new projects are scheduled from Start Date or from Completion Date when they are created.
|
User Time Off | Determine whether the time off of the Primary Assignee of a task adjusts the planned dates for that task on a project.
Consider the following when selecting options for this setting:
|
Project timelines will be automatically re-calculated |
Determine when the timeline of a project is recalculated. For information about recalculating the project timeline, see Recalculate project timelines. The following options are enabled by default. You can select one or more of the following settings:
|
When multiple users are assigned to a task use the schedule of the |
If a project does not have a schedule assigned or if the users assigned to its tasks do not have a Schedule assigned to them, Workfront uses the system default schedule to calculate the timeline of the tasks. If you assign multiple users to the same task in a project has an assigned schedule—and the users assigned to the tasks also have a schedule assigned to them—Workfront uses the following schedules:
For more information about schedules, see Create a schedule. |
Timeline Calculations |
These 2 options convert days to hours, or weeks to days. For example, if you have a task with 8 Planned Hours and the duration is calculated based on Planned Hours, Workfront converts those hours into days in order to show the Duration as days. From the Typical work days per week field, Workfront calculates the Full Time Equivalent (FTE) value for your system. This is what Workfront uses when calculating allocations for users. These values are used when you are planning projects timelines, budgeting for resources, or logging time against projects. They are not used when you are establishing timesheets for users in the system, as described in Configure timesheet and hour preferences. NOTE: Workfront administrators cannot unlock Timeline Calculations preferences. |
Custom Quarters |
Configure custom yearly quarters for the users who will be working on projects. Custom quarters are usually quarters that do not match the traditional breakdown of quarters during a calendar year. You can add multiple custom quarters. For more information, see Enable custom quarters for projects. NOTE: Workfront administrators cannot unlock Custom Quarters preferences. |
You can create a Business Case for newly created projects associated with the group to submit project requests. You can define preferences to determine which areas are visible on the Business Case form. We recommend that you enable these options so that other tools, such as the Portfolio Optimizer, update properly. For more information about what each field displays, see Define a Business Case.
After the Workfront administrator enables the sections on the Business Case, a Project Owner can then create a Business Case at the project level. For information about creating a Business Case, see Create a Business Case for a project.
Configure any of the following preferences for newly created projects associated with the group:
After a project has been marked as Complete, people can still |
Determine the rules for your organization (or group, if you are configuring project preferences for a group) regarding whether a task or an issue can be deleted after the project status has been marked Complete.
|
After a Project is marked Complete, Dead, or it is Pending Approval, people can still |
Determine the rules for your organization (or group, if you are configuring project preferences for a group) regarding what happens to tasks, issues, documents, and other objects in a project after the project status has been marked Complete, Dead, or is Pending Approval.
|