Send and schedule projects

You can send Adobe Analytics projects as files to selected users by email. You can send files ad hoc, or you can configure files to be sent on a schedule. Files can be sent in CSV or PDF format.

Any tags applied to the project are automatically applied to the export.

Other methods of exporting Adobe Analytics data are also available, as described in Export overview.

Send file

Send file

To send a file ad-hoc to recipients by email:

  1. Select Share > Send file.

  2. Specify the file type:

    • CSV: Choose this option if you want plain-text data.
    • PDF: Choose this option if you want the downloaded file to contain all the displayed (visible) tables and visualizations in the project.
  3. (Optional) Use Description to add a description to include in the email.

  4. Add recipients or groups. You can also enter email addresses.

  5. (Optional) Select Show scheduling options to schedule a file export.

  6. Click Send Now. Select Cancel to cancel.

Schedule file export schedule

To send a file on a schedule to recipients by email

  1. Select Share > Schedule file export.

  2. Specify the file type:

    • CSV: Choose this option if you want plain-text data.
    • PDF: Choose this option if you want the downloaded file to contain all the displayed (visible) tables and visualizations in the project.
  3. (Optional) Use Description to add a description to include in the email.

  4. Add recipients or groups. You can also enter email addresses.

  5. (Only for Healthcare Shield customers) Provide a password to password-protect a scheduled report.

  6. Ensure Show scheduling options is selected.

  7. Select a Frequency. You can select between:

    table 0-row-2 1-row-2 2-row-2 3-row-2 4-row-2 5-row-2 6-row-2 7-row-2
    Frequency Options
    Send hourly Enter a value for Send every number of hours.
    Send daily Select a Daily frequency: Send every day, Send every weekday, or Custom frequency.
    If you select Custom frequency, enter a value for Send every number of days.
    Send weekly Enter a value for Send every number of weeks. And select a Day of week.
    Send monthly by day of the week Select a Day of week and a Week of month.
    Send monthly by day of the month Select a value from Send on this day of the month.
    Send yearly by day of the month Select a Day of week, select a Week of month, and select a Monthly of year.
    Send yearly by specific date Select a Month of year and select a value from Send on this day of the month.
  8. Enter a start date in Starting on. Alternatively, select Calendar to pick a start date from the calendar.

  9. Enter an end date in Ending on. Alternatively, select Calendar to pick an end date from the calendar.

  10. Select Send on schedule. Select Cancel to cancel.

Scheduled projects manager manager

Scheduled Analysis Workspace projects can be managed from the main interface, using Components > Scheduled Projects. For more information, see Scheduled projects.