This page describes all Resource Management enhancements made with the 22.2 release to the Preview environment. These enhancements will be made available in the Production environment
the week of April 4, 2022.
For a list of all changes available with the 22.2 release, see 22.2 Release overview.
To improve your experience when using the Workload Balancer, we have introduced the following enhancements:
For more information about navigating the Workload Balancer, see Navigate the Workload Balancer.
To make assigning work items easier and more accurate, you can now make advanced assignments when you assign work items manually in the Workload Balancer. Prior to this enhancement, you could access Advanced Assignments when editing items, from the items’ headers, or in lists.
For more information, see Assign work manually using the Workload Balancer.
To provide more accurate information in resource management tools, we have changed the formula that Workfront uses to calculate user availability when the Workfront administrator selects The Default Schedule in Resource Management Preferences. With the new update, Workfront uses the following formula to calculate user availability:
User Available Hours = (Default Schedule Hours - Exceptions) * FTE - Time off hours
Prior to this update, Workfront used the following formula to calculate user availability when The Default Schedule was selected:
User Available Hours = (Default Schedule Hours - (Schedule Exceptions + Time off hours)) * User FTE value
For more information, see Configure Resource Management preferences.