Difference between Projected and Estimated Dates
The difference between Projected and Estimated Dates is:
-
Projected Dates are affected by a user making the following updates on the task:
- Add a Constraint Date by adding a fixed Task Constraint
- Add a Commit Date
-
Estimated Dates only take into account the real progress on a task in a given point in time.
Example: If we have a task that has a Planned Start Date of September 20 and a Planned Completion Date of September 24, and it has Must Finish On Constraint, the Projected Completion Date September 24. This task has a Duration of 4 days.
The Estimated Completion Date is calculated based on the current progress of the work on the task. So, if today is September 23 and the task has not started yet, the Estimated Completion Date is September 27 (it should be completed after 4 days, assuming that the work is started today).
If the task is 50% completed today, the Estimated Completion Date is on September 25 (it should be completed after 2 days which is half of the Duration of the task).
Understand when Projected Dates update on tasks
The Projected Dates can either match other task dates, or they are a calculation done by Workfront that takes into consideration the real-life progress of the task.
The following list displays several scenarios when the Projected Dates of tasks are changed during the life of a project depending on what happens in real life to the task:
-
When a task is marked as Complete:
Projected Dates = Estimated Dates = Actual Dates
-
When a task has an Actual Start Date:
Projected Start Date = Estimated Start Date = Actual Start Date
-
When a task does not have an Actual Start Date, but there is a forced constraint on the Planned Start Date (Must Start On) that is in the future:
Projected Start Date = Constraint Date
For information about Constraint Date, see Glossary of Adobe Workfront terminology.
-
When a task does not have an Actual Start Date and the task does not have a forced constraint date:
Projected Start Date = the next available date in the future that falls within working schedule
-
When the assignee updates the Commit Date:
Projected Completion Date = Commit Date
For information about Commit Date, see Commit Date overview.
-
When the task does not have an updated Commit Date and the task has a forced constraint (Must Finish On) for the Planned Completion Date that is in the future:
Projected Completion Date = Constraint Date
-
When a task does not have an updated Commit Date, a forced constraint date in the future, or it has a Constraint Date in the past:
Projected Completion Date = system calculation for the Completion Date based on the current progress and the work left to be done