Task constraints determine when a task should start and end on a project. For more information, see Task Constraint overview.
You must have the following to change the Task Constraint of a task:
Adobe Workfront plan* | Any |
Adobe Workfront license* | Work or higher |
Access level configurations* | View or higher access to Projects Edit access to Tasks Note: If you still don't have access, ask your Workfront administrator if they set additional restrictions in your access level. For information on how a Workfront administrator can modify your access level, see Create or modify custom access levels. |
Object permissions | Manage access to the task For information on requesting additional access, see Request access to objects . |
*To find out what plan, license type, or access you have, contact your Workfront administrator.
Click Main Menu > Projects, then click a project to access it.
Click the Tasks section in the left panel.
Click Task Details in the left panel, then in the Overview area click Task Constraint.
Select from the following options
Fixed Dates | For information, see Task Constraint overview: Fixed Dates. |
---|---|
Must Start On | For information, see Task Constraint overview: Must Start On. |
Must Finish On | For information, see Task Constraint overview: Must Finish On. |
As Soon As Possible | For information, see Task Constraint overview: As Soon As Possible. |
As Late As Possible | For information, see Task Constraint overview: As Late As Possible. |
Earliest Available Time | For information, see Task Constraint overview: Earliest Available Time. |
Latest Available Time | For information, see Task Constraint overview: Latest Available Time. |
Start No Later Than | For information, see Task Constraint overview: Start No Later Than. |
Start No Earlier Than | For information, see Task Constraint overview: Start No Earlier Than. |
Finish No Later Than | For information, see Task Constraint overview: Finish No Later Than. |
Finish No Earlier Than | For information, see Task Constraint overview: Finish No Earlier Than. |
Click Save Changes.