Baselines are snapshots of what the performance of a project looked like at a given moment in time. They store key pieces of information about the project, like key dates, progress, cost and revenue values.
When you create a baseline, the task information is also captured on the baseline tasks of that baseline.
For information about creating project baselines, see Create project baselines.
You can create Baseline or Baseline Task reports to view information captured about the project or the tasks at a given time.
In addition to name and date information, baselines and baseline tasks include financial information about the project or tasks. The lists below display the financial information of the project and of the tasks that is accessible from the Baseline or the Baseline Task objects.
For information about what each field displays, see Glossary of Adobe Workfront terminology.
The following project financial information is accessible from the Baseline object in a Baseline report:
Planned Expense Cost
Planned Labor Cost
Planned Risk Cost
Actual Expense Cost
Actual Labor Cost
Budgeted Cost
Resource Planner Budgeted Labor Cost
The Resource Planner Budgeted Labor Cost is the Labor Cost of the project based on the hours budgeted for the project in the Resource Planner at the time when the baseline was created.
Fixed Cost
Planned Revenue
Actual Revenue
Project Fixed Revenue
Planned Benefit
EAC
Planned Cost
Cost Performance Index (SPI)
Cost Schedule Performance Index (CSI)
Schedule Performance Index (CPI)
The following task financial information is accessible from the Baseline Task object in a Baseline Task report: