Key takeaways
- Definition of Task Duration: Task duration is the difference between a task’s planned start date and planned completion date, representing the time window for completing the work.
- Impact on Project Timeline: Task durations directly affect the overall project length and planned completion date, making them crucial for accurate project planning.
- Use of Predecessors: Planned start and completion dates are calculated using task durations and predecessors, ensuring a dynamic and flexible timeline.
- Avoid Manual Constraints: Manually setting start or completion dates creates task constraints, which can prevent automatic adjustments when durations or predecessors change.
- Resource Management: Durations are essential for Workfront’s resource management and scheduling tools, enabling accurate resource estimates and team availability planning.