View: Planned Hours vs. Actual Hours per assignment in a task view

This task view displays the total Planned Hours of a task, the number of Planned Hours allocated to each assignee, the total Actual Hours, and the number of Actual Hours logged by each assignee.

multi_assignment_budget_vs_actual_for_tasks.png

Access requirements

You must have the following access to perform the steps in this article:

Adobe Workfront plan*

Any

Adobe Workfront license*

Plan

Access level configurations*

Edit access to Reports, Dashboards, Calendars

Edit access to Filters, Views, Groupings

Note: If you still don't have access, ask your Workfront administrator if they set additional restrictions in your access level. For information on how a Workfront administrator can modify your access level, see Create or modify custom access levels.

Object permissions

Manage permissions to a report

For information on requesting additional access, see Request access to objects .

*To find out what plan, license type, or access you have, contact your Workfront administrator.

View Planned Hours vs. Actual Hours per assignment in a task View

  1. Go to a list of tasks.

  2. From the View drop-down menu, select New View.

  3. In theColumn Preview area, eliminate all columns except for one.

  4. Click the header of the remaining column, then click Switch to Text Mode.

  5. Mouse over the text mode area, and click Click to edit text.

  6. Remove the text you find in the Text Mode box, and replace it with the following code:

    column.0.descriptionkey=name<br>column.0.isInlineEditable=false<br>column.0.link.linkproperty.0.name=ID<br>column.0.link.linkproperty.0.valuefield=ID<br>column.0.link.linkproperty.0.valueformat=int<br>column.0.link.lookup=link.view<br>column.0.link.valuefield=objCode<br>column.0.link.valueformat=val<br>column.0.linkedname=direct<br>column.0.listsort=string(name)<br>column.0.namekey=name.abbr<br>column.0.querysort=name<br>column.0.section=0<br>column.0.shortview=false<br>column.0.stretch=0<br>column.0.valuefield=name<br>column.0.valueformat=HTML<br>column.0.width=150<br>column.1.descriptionkey=workrequired<br>column.1.isInlineEditable=false<br>column.1.linkedname=direct<br>column.1.listsort=doubleAsDouble(workRequired)<br>column.1.namekey=workrequired.abbr<br>column.1.querysort=workRequired<br>column.1.section=0<br>column.1.shortview=false<br>column.1.stretch=0<br>column.1.valuefield=workFieldLong<br>column.1.valueformat=compound<br>column.1.viewalias=workrequired<br>column.1.width=100<br>column.2.listdelimiter=<br>column.2.listmethod=nested(assignments).lists<br>column.2.name=Wrk Assignment(s)<br>column.2.stretch=0<br>column.2.type=iterate<br>column.2.valueexpression=CONCAT(right(CONCAT('~~~',{assignmentPercent}),3),'% (', {workRequired}/60 ,' Hours) - ',{assignedTo}.{name})<br>column.2.valueformat=HTML<br>column.2.width=300<br>column.3.descriptionkey=actualworkrequired<br>column.3.isInlineEditable=false<br>column.3.linkedname=direct<br>column.3.listsort=intAsInt(actualWorkRequired)<br>column.3.namekey=actualworkrequired.abbr<br>column.3.querysort=actualWork<br>column.3.section=0<br>column.3.shortview=false<br>column.3.stretch=100<br>column.3.valuefield=actualWorkFieldLong<br>column.3.valueformat=compound<br>column.3.viewalias=actualworkrequired<br>column.3.width=100<br>column.4.listdelimiter=<br>column.4.listmethod=nested(hours).lists<br>column.4.name=Actual Hours<br>column.4.stretch=0<br>column.4.type=iterate<br>column.4.valueexpression=CONCAT('(', {hours} ,' Hours) - ',{owner}.{name})<br>column.4.valueformat=HTML<br>column.4.width=300
    
  7. Click Save View.