Filter: display incomplete cross-project successors

This task filter returns incomplete cross-project successors.

Access requirements

Expand to view access requirements for the functionality in this article.
table 0-row-2 1-row-2 2-row-2 3-row-2 layout-auto html-authored no-header
Adobe Workfront package Any
Adobe Workfront license

Contributor or Request to modify a filter

Standard or Plan to modify a report

Access level configurations

Edit access to Reports, Dashboards, Calendars to modify a report

Edit access to Filters, Views, Groupings to modify a filter

Object permissions Manage permissions to a report

For more detail about the information in this table, see Access requirements in Workfront documentation.

Filter cross-project successors

To apply this filter:

  1. Go to a list of tasks.

  2. From the Filter drop-down menu, select New filter.

  3. Click Text mode.

  4. In the area displayed, paste the following code:

    percentComplete=100
    percentComplete_Mod=ne
    successorsMM:projectID=FIELD:projectID
    successorsMM:projectID_Mod=ne
    
  5. Click Apply > Save as new.