The following are frequently asked questions about projects.
In order to use the insert options, the task list must be sorted by number. To sort the column by number, click # in the column header to the left of Task Name to resort the task by number.
The Actual Completion Date represents the date and time the work is completed. For more information, see Overview of the project Actual Completion Date.
To use the indent/ outdent button, ensure the tasks are sorted by the task number and there are no Groupings applied.
I get the following error message when I try to mark my project complete:
You cannot change the status of a project to complete if you have any of the following on your project:
If the project has the Completion Mode set to Automatic, once all the tasks and issues are completed, the status of the project automatically turns to Complete and you cannot modify it to any other status. The Completion Mode of the project must be set to Manual to be able to turn a complete project to Current. For information, see Project status will not change from Complete to Current.
Although I have the correct permissions, the Add Projects button is missing on the Projects tab of the Portfolio.
This is caused by the Portfolio Status being Inactive. To change the status of the Portfolio:
Click on Portfolio Details > Overview.
Change the Status to Active.
Click Save.
The Add Projects button should now be visible on the Projects tab.
Resource Managers automatically receive Manage access to projects. Removing the user from the Resource Manager role does not remove their Manage sharing access.
The project statuses change because of the default statuses of the Group. When you add a group to a project, it changes the list of statuses to the default statuses set for the group.
For more information, see the article Create or edit a status.
Budget Status will show whether or not the project is currently added to the Capacity planner and if the budget calculation was completed.
The following are Budget Statuses:
The Adobe Workfront administrator restricted you to viewing only Companies, Groups & Teams that you belong to in your Access Level of the. The team that the you are looking for is not one of the teams that you belong to.
For information about enabling a user to view all teams in the system, see Create or modify custom access levels.