Projects in Adobe Workfront and Microsoft Project are mostly compatible. Using the two applications, you can do the following:
For more information about importing projects from Microsoft Project in to Workfront, see Import a project from Microsoft Project.
For more information about exporting a project from Workfront to import it into Microsoft Project, see Export a project to Microsoft Project.
When performing such imports of data, it is important to understand how information translates from one application to the other. Most times, you will have to make some manual modifications to the project, after you complete the import.
Planned dates do not always correspond between both systems. Discrepancies can be accounted for through schedule and differences in system preferences between Workfront and Microsoft Project. These date discrepancies can also result in differences in effort, duration, and percent complete.
Microsoft Project Field | Workfront Field |
---|---|
Project Title | Project Name |
Start and Finish Dates | Planned Start and Completion Dates |
Task Name | Task Name |
Task Duration | Task Planned Duration |
Task Work | Task Planned Hours |
Task % Complete | Task % Complete (based on the Duration of the task) |
Task Work % Complete | Task % Complete (based on the Planned Hours of the task) |
Scheduled Start and Finish | Planned Start and Completion Dates |
Actual Start and Finish | Actual Start and Completion Dates |
Resource Name | Task Assignment |
Assignment Units | Assignment Allocation Percentage |
Task Note | Task Description |
Predecessor | Predecessor |
There are a number of project fields that are not imported to or exported from Workfront.
These fields include but are not limited to the following:
Document attachments
Custom fields (at the project or task levels)
Workfront notes
Issues
Negative lag in tasks with a Start/ Finish predecessor relationship (tasks are imported without the lag)
Assignments
Task Constraints
Because Constraints do not map between Microsoft Project and Workfront, ensure that there are predecessor relationships between the tasks. Otherwise, the Planned Start and Planned Completion Dates of the tasks might not accurate in the imported project.