You can manually update the Status of a project to any other status, if needed.

You can manually update the Status of a project to a status that equates Complete only when the Completion Mode of the project is set to Manual.

Otherwise, Adobe Workfront automatically marks the project as Complete when all the tasks and issues of the project are completed and approved.

For more information about the project’s Completion Mode, see Edit projects.

Access requirements

You must have the following access to perform the steps in this article:

Adobe Workfront plan
Any
Adobe Workfront license*

New: Standard

Or

Current: Plan

Access level configurations
Edit access to Projects
Object permissions
Manage permissions on the project

*To find out what plan, license type, or access you have, contact your Workfront administrator. For more information, see Access requirements in Workfront documentation.

Considerations about updating to specific statuses

  • When updating a project to Complete: Ensure that all tasks and issues are completed on the project. You cannot select the Complete status for a project, or any other status that equates Complete when there are tasks or issues that have not been completed on the project. This includes approving any task or issue that is in a Complete-Pending Approval status.
  • When updating a project from Complete to Current: If all the tasks and issues on the project are completed, ensure that the project’s Completion Mode is set to Manual. If the project’s Completion Mode is Automatic, the status of the project remains Complete.

Change project status

  1. Go to the project whose status you want to update.

  2. In the project header, click the name of the status in the Status field, then select a new status.

    Change project status

    Or

    Click the More menu More menu next to the name of the project and click Edit and select a new status in the Status field, then click Save.

    The project status updates to the status you selected.