已弃用项目计划持续时间

WITH task_daily_work as (
    SELECT
        taskid,
        projectid,
        planneddurationminutes,
        percentcomplete,
        calendardate,
        (planneddurationminutes - (planneddurationminutes * percentcomplete)) as remainingDurationMinutes
    FROM tasks_daily_history
)

SELECT
    p.name,
    p.projectid,
    sum(tdw.planneddurationminutes) as projectTotalWork,
    sum(tdw.remainingDurationMinutes) as projectRemainingWork,
    tdw.calendardate
FROM projects_current p
    JOIN task_daily_work tdw ON p.projectid = tdw.projectid
GROUP BY p.projectid, p.name, tdw.calendardate

项目计划持续时间已停用:燃尽

WITH task_daily_work as (
    SELECT
        taskid,
        projectid,
        planneddurationminutes,
        percentcomplete,
        calendardate,
        (planneddurationminutes - (planneddurationminutes * percentcomplete)) as remainingDurationMinutes
    FROM tasks_daily_history
)

SELECT
    p.name,
    p.projectid,
    sum(tdw.planneddurationminutes) as projectTotalWork,
    sum(tdw.remainingDurationMinutes) as projectRemainingWork,
    tdw.calendardate
FROM projects_current p
    JOIN task_daily_work tdw ON p.projectid = tdw.projectid
GROUP BY p.projectid, p.name, tdw.calendardate