Tasks: Cannot change Planned Completion Date of a task
NOTE
This issue has been closed because it is working as designed.
When a user attempts to change the Planned Completion Date of a task, the field is unresponsive.
This has been reported in the following areas:
- The task header
- The Task Details area
Workaround
Do one of the following:
- In the Task Details area, change the Task Constraint to “Must Finish On”, and then change the Planned Completion Date.
- Change the Planned Completion Date inline in the task list.
First reported on October 11, 2022.
recommendation-more-help