What is the primary benefit of using predecessors in Workfront?
false
  1. They allow tasks to be completed in any order, providing flexibility.
  2. They automatically assign tasks to users with the necessary skills.
  3. They eliminate the need for setting task durations.
  4. They establish the sequence of tasks, ensuring certain tasks are completed before others can begin.
v6/oDutSs75W1RSbEQ7Vfuoq4FXzuwRbFl+jgLzKHHA=
Your answer is correct
Your answer is incorrect
How does the Gantt chart and Critical Path feature in Workfront benefit project management?
false
  1. They automatically resolve all project issues.
  2. They provide a visual timeline and highlight tasks that could delay the project if they slip.
  3. They assign tasks to users based on their availability.
  4. They ensure all tasks are completed simultaneously.
moOsclWJjnjdPYNanYV5B6TA4CkVCDzNNyI/H9p/Ojk=
Your answer is correct
Your answer is incorrect
What are some advantages of using the Work Effort feature in Workfront?
true
  1. It helps estimate planned hours for tasks based on their duration.
  2. It automatically assigns tasks to the most skilled user.
  3. It allows for inline and bulk editing of task durations.
  4. It provides a visual representation of task dependencies.
W7VZQ6yBvG6RYbLycKsfBPoguFkDbQi0XEuGMlSSOKc=,ydVRAdLxI6z7l5nfTJk7U0oQM9UyfiVGTuIHJAP7oLU=
Your answer is correct
Your answer is incorrect