What is the primary benefit of using predecessors in Workfront?
false
- They allow tasks to be completed in any order, providing flexibility.
- They automatically assign tasks to users with the necessary skills.
- They eliminate the need for setting task durations.
- They establish the sequence of tasks, ensuring certain tasks are completed before others can begin.
v6/oDutSs75W1RSbEQ7Vfuoq4FXzuwRbFl+jgLzKHHA=
Your answer is correct
Your answer is incorrect
How does the Gantt chart and Critical Path feature in Workfront benefit project management?
false
- They automatically resolve all project issues.
- They provide a visual timeline and highlight tasks that could delay the project if they slip.
- They assign tasks to users based on their availability.
- They ensure all tasks are completed simultaneously.
moOsclWJjnjdPYNanYV5B6TA4CkVCDzNNyI/H9p/Ojk=
Your answer is correct
Your answer is incorrect
What are some advantages of using the Work Effort feature in Workfront?
true
- It helps estimate planned hours for tasks based on their duration.
- It automatically assigns tasks to the most skilled user.
- It allows for inline and bulk editing of task durations.
- It provides a visual representation of task dependencies.
W7VZQ6yBvG6RYbLycKsfBPoguFkDbQi0XEuGMlSSOKc=,ydVRAdLxI6z7l5nfTJk7U0oQM9UyfiVGTuIHJAP7oLU=
Your answer is correct
Your answer is incorrect