This task grouping allows you to group tasks by the Project Sponsor.
You must have the following access to perform the steps in this article:
Adobe Workfront plan* | Any |
Adobe Workfront license* | Request to modify a grouping Plan to modify a report |
Access level configurations* | Edit access to Reports, Dashboards, Calendars to modify a report Edit access to Filters, Views, Groupings to modify a grouping NOTE If you still don’t have access, ask your Workfront administrator if they set additional restrictions in your access level. For information on how a Workfront administrator can modify your access level, see Create or modify custom access levels. |
Object permissions | Manage permissions to a report For information on requesting additional access, see Request access to objects . |
*To find out what plan, license type, or access you have, contact your Workfront administrator.
To apply this grouping:
Go to list of tasks.
In the Grouping drop-down menu, select New Grouping.
Click Switch to Text Mode.
Remove the text you see in the text editing window.
Copy and paste the following code in the text editing window:
group.0.name=Project Sponsor<br>group.0.valuefield=project:sponsor:name<br>group.0.valueformat=string
Click Save Grouping.