This task filter returns incomplete cross-project successors.
You must have the following access to perform the steps in this article:
Adobe Workfront plan* | Any |
Adobe Workfront license* | Request to modify a filter Plan to modify a report |
Access level configurations* | Edit access to Reports, Dashboards, Calendars to modify a report Edit access to Filters, Views, Groupings to modify a filter NOTE If you still don’t have access, ask your Workfront administrator if they set additional restrictions in your access level. For information on how a Workfront administrator can modify your access level, see Create or modify custom access levels. |
Object permissions | Manage permissions to a report For information on requesting additional access, see Request access to objects . |
*To find out what plan, license type, or access you have, contact your Workfront administrator.
To apply this filter:
Go to a list of tasks.
From the Filter drop-down menu, select New Filter.
ClickSwitch to Text Mode.
In the Set Filter Rules for your Report area, paste the following code:
percentComplete=100
percentComplete_Mod=ne
successorsMM:projectID=FIELD:projectID
successorsMM:projectID_Mod=ne
Click Save Filter.